310 S WESTGATE AVE 90049

Certificate Information: 310 S WESTGATE AVE 90049

Application / Permit
23010-20000-01781
Plan Check / Job No.
B23VN05377
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 16'3" X 11'9-1/2" IRREGULAR SHAPED DETACHED PATIO COVER WITH DECK ABOVE , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/9/2023
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 RARES BODEA
Corrections Issued 5/1/2023 RARES BODEA
Quality Review Completed 5/4/2023 STEVEN KIM
Building Plans Picked Up 5/4/2023 APPLICANT
Plan Check Approved 11/9/2023 RARES BODEA
Issued 11/9/2023 APPLICANT
CofO in Progress 4/23/2025 CARLOS MATAMOROS
CofO Issued 4/24/2025 RICHARD STEINBACH
Permit Finaled 4/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 5/5/2023 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 5/8/2023 DENNIS BRAGIN
Specific Plan Cleared 5/18/2023 FREDDY GARCIA
Low Impact Development (LID) Cleared 7/3/2023 SHAHIN KHAZEY
Miscellaneous Cleared 7/5/2023 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 7/5/2023 HISASHI KOBAYAKAWA
Watercourse Cleared 7/5/2023 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 11/9/2023 RARES BODEA

Contact Information

Contractor Structure Home; Lic. No.: 721043-B 23974 CRAFTSMAN ROAD      CALABASAS, CA 91302
Engineer Padilla,, Juan Carlos; Lic. No.: C79760 647 ERBES ROAD      THOUSAND OAKS, CA 91362

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/17/2024 Partial Approval CARLOS MATAMOROS
Structural Steel Frame 4/17/2024 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/30/2024 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 4/30/2024 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 5/9/2024 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/9/2024 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/9/2024 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/15/2024 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 5/17/2024 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 6/4/2024 Conditional Approval MICHAEL PELHAM
FLOOD-Proofing Certificate 12/3/2024 Approved CARLOS MATAMOROS
Final 12/3/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 12/3/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 12/3/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 12/3/2024 Approved CARLOS MATAMOROS
Wood Frame 12/3/2024 Approved CARLOS MATAMOROS
Final 3/11/2025 Corrections Issued CARLOS MATAMOROS
Final 4/18/2025 Conditional Approval STEPHANIE SWANSON
Final 4/21/2025 OK to Issue CofO CARLOS MATAMOROS