2242-2244 S PENMAR AVE 90291

Certificate Information: 2242-2244 S PENMAR AVE 90291

Application / Permit
23010-20000-01776
Plan Check / Job No.
B23VN05334
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 24'-8" X 37' TWO-STORY (2) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g) AND SB 897 and AB 2221 ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/7/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/4/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/5/2023 OMID HEDAYAT
Building Plans Picked Up 5/8/2023 APPLICANT
Plan Check Approved 6/9/2023 SEWADA ZADOORAN MILAGARDI
Issued 7/7/2023 APPLICANT
CofO in Progress 8/15/2024 HERBERT GIRON
Permit Finaled 8/15/2024 RICHARD STEINBACH
CofO Issued 8/15/2024 RICHARD STEINBACH
Permit Finaled 8/15/2024 RICHARD STEINBACH

Permit Application Clearance Information

"Q" conditions Cleared 5/9/2023 DANG NGUYEN
Address approval Cleared 5/9/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/9/2023 ANTHONY MAINEZ
Sewer availability Cleared 5/9/2023 ANTHONY MAINEZ
Low Impact Development (LID) Cleared 5/18/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/19/2023 DINAH GARIN
Specific Plan Cleared 5/23/2023 PEDRO AYALA

Contact Information

Architect Nigosian,, Michael Nickolas; Lic. No.: C35308 75-572 PAINTED DESERT DRIVE      INDIAN WELLS, CA 92210
Contractor Tsfira Zohar; Lic. No.: 860984-B 8222 MELROSE AVENUE   # 207    LOS ANGELES, CA 90046
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/17/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 8/22/2023 Partial Approval HERBERT GIRON
Underground Mechanical 8/22/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 9/11/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 9/13/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 9/21/2023 Conditional Approval HERBERT GIRON
Special/Order Compliance 9/21/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 10/17/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Partial Approval HERBERT GIRON
Deputy Wood Construction 1/16/2024 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 1/18/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/18/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 2/16/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 2/16/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/27/2024 Approved HERBERT GIRON
HVAC-Rough 2/27/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 2/27/2024 Approved HERBERT GIRON
HVAC-Rough 3/8/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval HERBERT GIRON
HVAC-Rough 3/18/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 3/28/2024 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 4/8/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Approved HERBERT GIRON
Green Building Rough 4/8/2024 Approved HERBERT GIRON
Insulation 4/8/2024 Corrections Issued HERBERT GIRON
Drywall Nailing 4/18/2024 Approved HERBERT GIRON
Insulation 4/18/2024 Approved HERBERT GIRON
Light Gage Steel Frame 4/18/2024 Approved HERBERT GIRON
Shower Pan 5/1/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 5/3/2024 Approved HERBERT GIRON
PLUMBING-Final 6/24/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 6/26/2024 Corrections Issued HERBERT GIRON
HVAC-Final 6/27/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/27/2024 Corrections Issued HERBERT GIRON
HVAC-Final 7/2/2024 Approved HERBERT GIRON
PLUMBING-Final 7/2/2024 Approved HERBERT GIRON
ELECTRICAL-Final 7/3/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 7/25/2024 Approved HERBERT GIRON
Service/Power Release 7/25/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/8/2024 Approved HERBERT GIRON
Final 8/8/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/8/2024 Approved HERBERT GIRON
Green Building Final 8/8/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Not Required HERBERT GIRON
Smoke Detectors 8/8/2024 Approved HERBERT GIRON
Final 8/14/2024 OK to Issue CofO HERBERT GIRON