9929 W ANTHONY PL 90210

Certificate Information: 9929 W ANTHONY PL 90210

Application / Permit
23010-20000-01765
Plan Check / Job No.
B23VN05250
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 18'0"X12'6" 1-STORY RECREATION ROOM WITH SHOWER THAT HAS EXTERIOR ACCESS ONLY FOR POOL. SEE COMMENTS <1 OF 3>
Permit Issued
Issued on 12/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 MARVEL DELACRUZ
Corrections Issued 4/29/2023 MARVEL DELACRUZ
Quality Review Completed 5/5/2023 OMID HEDAYAT
Building Plans Picked Up 5/8/2023 APPLICANT
Plan Check Approved 12/12/2023 MARVEL DELACRUZ
Issued 12/21/2023 APPLICANT
CofO in Progress 7/22/2025 SEAN HAUPT
Permit Finaled 7/29/2025 RICHARD STEINBACH
CofO Issued 7/29/2025 RICHARD STEINBACH
Permit Finaled 7/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 9/7/2023 TOMMY YIN
BHO/Hillside ordinance Cleared 9/27/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 9/27/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 9/27/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 9/27/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 9/27/2023 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 9/27/2023 AHMED AMARRAGY
Sewer availability Cleared 9/27/2023 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 10/2/2023 AHMED AMARRAGY
ZI Cleared 10/4/2023 SPENCER WEJROWSKI
Distance to fire station Cleared 11/15/2023 LAVEON RIDER
Hydrant and Access approval Cleared 11/15/2023 LAVEON RIDER

Contact Information

Contractor Brody Inc; Lic. No.: 409492-B 14140 MOORPARK ST #400      SHERMAN OAKS, CA 91423
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/17/2024 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 1/17/2024 Partial Approval BRENDAN LOONEY
Special/Order Compliance 1/17/2024 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 1/18/2024 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 1/18/2024 Not Ready for Inspection BRENDAN LOONEY
Deputy Reinf. Concrete 1/24/2024 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 7/1/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 7/25/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 7/31/2024 Approved SEAN HAUPT
Green Building Rough 7/31/2024 Approved SEAN HAUPT
Verify Sprinkler Sign Off 7/31/2024 Approved SEAN HAUPT
Insulation 8/8/2024 Not Ready for Inspection SEAN HAUPT
Insulation 8/9/2024 Approved SEAN HAUPT
Shower Pan 9/26/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 10/11/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 4/16/2025 Corrections Issued SEAN HAUPT
PLUMBING-Final 4/16/2025 Approved SEAN HAUPT
ELECTRICAL-Final 4/24/2025 Approved SEAN HAUPT
Smoke Detectors 4/24/2025 Approved SEAN HAUPT
HVAC-Final 6/26/2025 Approved SEAN HAUPT
Drywall Nailing 7/9/2025 Approved SEAN HAUPT
Final 7/9/2025 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 7/9/2025 Approved SEAN HAUPT
Green Building Final 7/9/2025 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Approved SEAN HAUPT
Service/Power Release 7/9/2025 Approved SEAN HAUPT
Final 7/21/2025 OK to Issue CofO SEAN HAUPT