13413 W GAGER ST 91331
Certificate Information: 13413 W GAGER ST 91331
- Application / Permit
- 23010-20000-01758
- Plan Check / Job No.
- B23VN05232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY 21'6" X 61' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK TO BE DONE PER WFPP.
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | RAMA DABADGE |
| Corrections Issued | 5/1/2023 | RAMA DABADGE |
| Building Plans Picked Up | 5/3/2023 | APPLICANT |
| Applicant returned to address corrections | 8/3/2023 | ANGELICA DAVE |
| Plan Check Approved | 8/17/2023 | MADISON ODELL |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 9/20/2024 | MICHEL ABAJAN |
| No Progress | 10/4/2024 | ROBERT GOLD |
| CofO in Progress | 10/4/2024 | ROBERT GOLD |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
| CofO Issued | 10/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 5/5/2023 | NATHAN ROMINE |
| ZI | Cleared | 5/5/2023 | NATHAN ROMINE |
| Address approval | Cleared | 5/11/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/22/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 7/11/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/26/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/17/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/17/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/17/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/6/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 2/6/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/8/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 2/8/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/7/2024 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 3/7/2024 | Approved | MICHEL ABAJAN |
| Insulation | 3/12/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/12/2024 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 3/28/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/28/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/16/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 4/16/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 6/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/4/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/28/2024 | Approved | MICHEL ABAJAN |
| Final | 6/28/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/28/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/28/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/28/2024 | Approved | MICHEL ABAJAN |
| Service/Power Release | 6/28/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/3/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 7/3/2024 | Approved | MICHEL ABAJAN |
| Special/Order Compliance | 10/8/2024 | Corrections Issued | MICHEL ABAJAN |