19511 W CANTARA ST 91335
Certificate Information: 19511 W CANTARA ST 91335
- Application / Permit
- 23010-20000-01753
- Plan Check / Job No.
- B23VN05221
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) 2-STORY SINGLE FAMILY DWELLING PER SENATE BILL 9 TWO UNIT DEVELOPMENT
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | DANIEL YIP |
| Corrections Issued | 5/18/2023 | DANIEL YIP |
| Quality Review Completed | 5/18/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/25/2024 | DANIEL YIP |
| Applicant returned to address corrections | 5/8/2024 | DANIEL YIP |
| Plan Check Approved | 6/25/2024 | DANIEL YIP |
| Plan Check Approved | 6/25/2024 | DANIEL YIP |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 8/27/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 9/19/2025 | JOHN JANSON |
| CofO Issued | 9/19/2025 | JOHN JANSON |
| Permit Finaled | 9/19/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2024 | EDGAR ALCARAZ |
| Permit | Cleared | 4/30/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 5/1/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 5/30/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 6/6/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | BRYAN GODINEZ |
| Senate Bill 9 | Cleared | 6/18/2024 | DANIEL CORONADO |
Contact Information
| Contractor | Riaan Construction; Lic. No.: 1113393-B | , |
| Engineer | Pachunuri,, Nalin Kumar; Lic. No.: C78970 | 21126 INGOMAR CT CANOGA PARK, CA 91304 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 6/27/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 6/27/2024 | Corrections Issued | JEFFREY BULL |
| Underground Mechanical | 6/27/2024 | Partial Approval | JEFFREY BULL |
| Deputy Wood Construction | 8/2/2024 | Conditional Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 8/6/2024 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Approved | SEAN WIRCH |
| HVAC-Rough | 8/6/2024 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 8/6/2024 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 8/27/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | JEFFREY BULL |
| Verify Sprinkler Sign Off | 8/27/2024 | Approved | JEFFREY BULL |
| Insulation | 9/5/2024 | Not Ready for Inspection | SCOTT SOBEL |
| Interior/Exterior Lathing | 9/5/2024 | Partial Approval | SCOTT SOBEL |
| Shower Pan | 9/5/2024 | Corrections Issued | SCOTT SOBEL |
| Insulation | 9/9/2024 | Approved | SCOTT SOBEL |
| Shower Pan | 9/9/2024 | Approved | SCOTT SOBEL |
| Drywall Nailing | 9/13/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 12/18/2024 | Approved | GEVORK IPCHYAN |
| Final | 4/15/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 4/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 4/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 4/15/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 8/26/2025 | Approved | ARUTYUN MADATYAN |
| Final | 8/26/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 8/26/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 8/26/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 8/26/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 8/26/2025 | Approved | ARUTYUN MADATYAN |