18114 W VALERIO ST 91335

Certificate Information: 18114 W VALERIO ST 91335

Application / Permit
23010-20000-01751
Plan Check / Job No.
B23VN05216
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE TO A DETACHED ADU WITH (N) ADDITION PER ORDINANCE
Permit Issued
Issued on 11/30/2023
Issuing Office
Current Status
Issued on 11/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/26/2023 APPLICANT
Assigned to Plan Check Engineer 5/1/2023 FERNANDO FLORES
Corrections Issued 5/2/2023 FERNANDO FLORES
Applicant returned to address corrections 11/17/2023 FERNANDO FLORES
Plan Check Approved 11/20/2023 LUKE GONZALES
Issued 11/30/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/26/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/28/2023 COLIN LOREDO
Sewer availability Cleared 8/28/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 11/14/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/18/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/1/2024 Partial Approval JEFFREY BULL
Footing/Foundation/Slab 4/15/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 9/9/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Approved JEFFREY BULL
HVAC-Rough 9/9/2024 Approved JEFFREY BULL
Insulation 9/27/2024 Corrections Issued JEFFREY BULL
Interior/Exterior Lathing 9/27/2024 Approved JEFFREY BULL
Drywall Nailing 10/17/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 2/3/2025 Approved ARUTYUN MADATYAN
Final 2/3/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 2/3/2025 Approved ARUTYUN MADATYAN
Green Building Rough 2/3/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 2/3/2025 Approved ARUTYUN MADATYAN