14928 W LABRADOR ST 91343

Certificate Information: 14928 W LABRADOR ST 91343

Application / Permit
23010-20000-01728
Plan Check / Job No.
B23VN05121
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Demo existing garage and build new 1200 sf ADU PER LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 10/25/2023
Issuing Office
Current Status
CofO Issued on 8/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 RAHEL BEYENE
Corrections Issued 5/25/2023 RAHEL BEYENE
Quality Review Completed 6/9/2023 MICHAEL PEREZ
Applicant returned to address corrections 10/11/2023 RAHEL BEYENE
Plan Check Approved 10/20/2023 RAHEL BEYENE
Issued 10/25/2023 APPLICANT
CofO in Progress 6/12/2024 JENNIFER RABUCHIN
No Progress 6/25/2024 ROBERT GOLD
CofO in Progress 6/25/2024 ROBERT GOLD
CofO in Progress 7/3/2024 ROBERT GOLD
CofO in Progress 8/2/2024 JENNIFER RABUCHIN
No Progress 8/16/2024 ROBERT GOLD
CofO in Progress 8/16/2024 ROBERT GOLD
CofO in Progress 8/16/2024 ROBERT GOLD
CofO in Progress 8/16/2024 ROBERT GOLD
CofO Issued 8/19/2024 DANIEL ORRANTE
Permit Finaled 8/19/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/27/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 7/31/2023 RYAN KIM
Sewer availability Cleared 7/31/2023 RYAN KIM
Hydrant and Access approval Cleared 8/28/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 9/19/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/20/2023 RYAN KIM
Hold Cleared 11/15/2023 CARMEN MERAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/20/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/20/2023 Partial Approval JENNIFER RABUCHIN
Special/Order Compliance 11/20/2023 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 11/30/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/30/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 11/30/2023 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 11/30/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 12/5/2023 Approved JOHN COLEMAN
Sewer 12/12/2023 Approved JENNIFER RABUCHIN
Underground Mechanical 12/12/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 1/18/2024 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved DANIEL ORRANTE
HVAC-Rough 1/18/2024 Approved DANIEL ORRANTE
PLUMBING-Rough 1/18/2024 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 1/24/2024 Approved JENNIFER RABUCHIN
Green Building Rough 1/24/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/24/2024 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 1/24/2024 Approved JENNIFER RABUCHIN
Deputy Wood Construction 1/29/2024 Conditional Approval ROBERT GOLD
Insulation 1/31/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 2/6/2024 Approved CHRISTOPHER ROJAS
Shower Pan 2/6/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/21/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 3/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 4/10/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 4/10/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 4/10/2024 Corrections Issued JENNIFER RABUCHIN
Final 5/21/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/21/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/21/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 5/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/21/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/29/2024 Approved JENNIFER RABUCHIN
Final 5/29/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 5/29/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/29/2024 Approved JENNIFER RABUCHIN
Service/Power Release 5/29/2024 Approved JENNIFER RABUCHIN