10813 N MEMORY PARK AVE 91345
Certificate Information: 10813 N MEMORY PARK AVE 91345
- Application / Permit
- 23010-20000-01727
- Plan Check / Job No.
- B23VN05119
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW DETACHED A STORY ADU PER LAMC 12.22A.33(c) and (d)
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 5/24/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/31/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 11/20/2023 | MARCELA FRANQUEZ |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 7/16/2024 | JENNIFER RABUCHIN |
| No Progress | 12/4/2024 | ROBERT GOLD |
| CofO in Progress | 1/13/2025 | ROBERT GOLD |
| CofO in Progress | 1/13/2025 | ROBERT GOLD |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2023 | RYAN KIM |
| Sewer availability | Cleared | 7/31/2023 | RYAN KIM |
| Low Impact Development (LID) | Cleared | 9/12/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/12/2023 | RYAN KIM |
| Construction near power lines | Cleared | 11/6/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/6/2023 | RIDWAN HARDY |
| Hold | Cleared | 1/24/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/25/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/25/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 1/31/2024 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/15/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/1/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/1/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/1/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 4/1/2024 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 4/1/2024 | Approved | JENNIFER RABUCHIN |
| Deputy Wood Construction | 4/3/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 4/4/2024 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 4/5/2024 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 4/8/2024 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 4/15/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/22/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/22/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/22/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/1/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 5/1/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/5/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Sewer | 6/5/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 6/5/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/25/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 6/25/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 6/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 6/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 6/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 6/25/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 6/25/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| Final | 7/3/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/3/2025 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 1/3/2025 | Approved | JENNIFER RABUCHIN |