11536 N WELK AVE 91331
Certificate Information: 11536 N WELK AVE 91331
- Application / Permit
- 23010-20000-01726
- Plan Check / Job No.
- B23VN05117
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) TWO STORY 36'-4" X 16'-6" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING SEE COMMENTS
- Permit Issued
- Issued on 4/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/18/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/19/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/7/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/12/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/2/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/3/2024 | APPLICANT |
| CofO in Progress | 3/28/2025 | MICHEL ABAJAN |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
| CofO Issued | 5/6/2025 | RUBEN SALAS |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 5/23/2023 | BRENNEN OBETO |
| Address approval | Cleared | 6/5/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 6/9/2023 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/12/2023 | MEGAN GODINEZ |
| Low Impact Development (LID) | Cleared | 8/3/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/4/2023 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 11/22/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/22/2023 | RIDWAN HARDY |
| Hold | Cleared | 5/29/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/31/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/21/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 9/3/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/6/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 9/6/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/6/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 9/6/2024 | Approved | MICHEL ABAJAN |
| Insulation | 9/18/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/18/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 9/18/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/23/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/9/2024 | Approved | MICHEL ABAJAN |
| Final | 2/28/2025 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 2/28/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 2/28/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/27/2025 | Approved | MICHEL ABAJAN |
| Final | 3/27/2025 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 3/27/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/27/2025 | Approved | MICHEL ABAJAN |