9963 N WISNER AVE 91345
Certificate Information: 9963 N WISNER AVE 91345
- Application / Permit
- 23010-20000-01703
- Plan Check / Job No.
- B23VN05056
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW 34' X 19' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | SELLA BENYAMIN |
| Corrections Issued | 5/16/2023 | SELLA BENYAMIN |
| Quality Review Completed | 5/23/2023 | STEVEN KIM |
| Applicant returned to address corrections | 8/31/2023 | SELLA BENYAMIN |
| Plan Check Approved | 10/3/2023 | SELLA BENYAMIN |
| No Progress | 10/17/2023 | SELLA BENYAMIN |
| Plan Check Approved | 10/19/2023 | SELLA BENYAMIN |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 4/8/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
| CofO Issued | 4/22/2025 | RUBEN SALAS |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/20/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 8/3/2023 | MEGAN PINKUS |
| Roof/Waste drainage to street | Cleared | 8/26/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/20/2023 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 2/2/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Wood Construction | 2/14/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/6/2024 | Corrections Issued | JOHN COLEMAN |
| HVAC-Rough | 3/6/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 3/6/2024 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 3/6/2024 | Approved | JOHN COLEMAN |
| Insulation | 3/12/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/18/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/5/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/11/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/11/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/11/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/6/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/6/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | JENNIFER RABUCHIN |
| Final | 12/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 12/12/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 3/27/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 3/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 4/3/2025 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 4/3/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 4/8/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 4/8/2025 | Approved | JENNIFER RABUCHIN |