7300 N FIRMAMENT AVE 91406

Certificate Information: 7300 N FIRMAMENT AVE 91406

Application / Permit
23010-20000-01701
Plan Check / Job No.
B23VN05054
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan New two stories 34 x 22' 3" Single Family Dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21 NFPA 13D sprinkler required. All work done per engineer.
Permit Issued
Issued on 8/7/2024
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 NAREG ATARIAN
Corrections Issued 9/25/2023 SEAN SHAHMIRI
Quality Review Completed 10/3/2023 OMID HEDAYAT
Applicant returned to address corrections 6/26/2024 NAREG ATARIAN
Applicant returned to address corrections 7/12/2024 NAREG ATARIAN
Applicant returned to address corrections 7/18/2024 NAREG ATARIAN
Plan Check Approved 7/29/2024 NAREG ATARIAN
Issued 8/7/2024 APPLICANT
CofO in Progress 1/15/2026 VINCENT HANLEY
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/17/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/30/2023 NIKKI ZULUETA
Senate Bill 9 Cleared 2/27/2024 ALEX VELA
ZA Case Cleared 2/27/2024 ALEX VELA
ZI Cleared 2/27/2024 ALEX VELA
Sewer availability Cleared 3/2/2024 BRYAN GODINEZ
Hydrant and Access approval Cleared 3/13/2024 MATTHEW CRAIG
Low Impact Development (LID) Cleared 4/19/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 5/2/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/23/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/23/2024 Approved VINCENT HANLEY
PLUMBING-Rough 8/23/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/16/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 10/16/2024 Approved JACK KARGODORIAN
Green Building Rough 10/16/2024 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 10/16/2024 Corrections Issued JACK KARGODORIAN
MERV13>=Rough 10/16/2024 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 10/16/2024 Corrections Issued JACK KARGODORIAN
Verify Sprinkler Sign Off 10/16/2024 Corrections Issued JACK KARGODORIAN
Wood Frame 10/16/2024 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 10/30/2024 Conditional Approval DAVID MATSON
Deputy Wood Construction 10/30/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 10/31/2024 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Rough 10/31/2024 No Access for Inspection VINCENT HANLEY
Green Building Rough 10/31/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 10/31/2024 No Access for Inspection VINCENT HANLEY
MERV13>=Rough 10/31/2024 No Access for Inspection VINCENT HANLEY
PLUMBING-Rough 10/31/2024 No Access for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 10/31/2024 No Access for Inspection VINCENT HANLEY
Wood Frame 10/31/2024 No Access for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 11/8/2024 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 11/8/2024 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Corrections Issued VINCENT HANLEY
Green Building Rough 11/8/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 11/8/2024 Partial Approval VINCENT HANLEY
MERV13>=Rough 11/8/2024 Approved VINCENT HANLEY
PLUMBING-Rough 11/8/2024 Corrections Issued VINCENT HANLEY
Verify Sprinkler Sign Off 11/8/2024 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 11/25/2024 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 11/25/2024 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 11/25/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 11/25/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/25/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 11/25/2024 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 1/9/2025 Approved VINCENT HANLEY
HVAC-Rough 1/9/2025 Approved VINCENT HANLEY
PLUMBING-Rough 1/9/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/13/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval VINCENT HANLEY
Insulation 1/13/2025 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 1/13/2025 Approved VINCENT HANLEY
Shower Pan 1/13/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/13/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/21/2025 Approved VINCENT HANLEY
Drywall Nailing 1/21/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/21/2025 Approved VINCENT HANLEY
Green Building Rough 1/21/2025 Approved VINCENT HANLEY
Insulation 1/21/2025 Approved VINCENT HANLEY
Final 6/23/2025 Corrections Issued VINCENT HANLEY
Green Building Final 6/23/2025 Approved VINCENT HANLEY
MERV13>=Final 6/23/2025 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 6/23/2025 Corrections Issued VINCENT HANLEY
Smoke Detectors 6/23/2025 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready WILLIAM WREN
ELECTRICAL-Final 10/21/2025 Corrections Issued VINCENT HANLEY
Final 10/21/2025 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 10/21/2025 Approved VINCENT HANLEY
MERV13>=Final 10/21/2025 Partial Approval VINCENT HANLEY
PLUMBING-Final 10/21/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 10/21/2025 Partial Approval VINCENT HANLEY
Smoke Detectors 10/21/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 1/14/2026 Approved VINCENT HANLEY
Final 1/14/2026 OK to Issue CofO VINCENT HANLEY
MERV13>=Final 1/14/2026 Approved VINCENT HANLEY
Service/Power Release 1/14/2026 Approved VINCENT HANLEY