7300 N FIRMAMENT AVE 91406
Certificate Information: 7300 N FIRMAMENT AVE 91406
- Application / Permit
- 23010-20000-01701
- Plan Check / Job No.
- B23VN05054
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan New two stories 34 x 22' 3" Single Family Dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21 NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 8/7/2024
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | NAREG ATARIAN |
| Corrections Issued | 9/25/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 10/3/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/26/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 7/12/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 7/18/2024 | NAREG ATARIAN |
| Plan Check Approved | 7/29/2024 | NAREG ATARIAN |
| Issued | 8/7/2024 | APPLICANT |
| CofO in Progress | 1/15/2026 | VINCENT HANLEY |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
| CofO Issued | 1/28/2026 | RUBEN SALAS |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Senate Bill 9 | Cleared | 2/27/2024 | ALEX VELA |
| ZA Case | Cleared | 2/27/2024 | ALEX VELA |
| ZI | Cleared | 2/27/2024 | ALEX VELA |
| Sewer availability | Cleared | 3/2/2024 | BRYAN GODINEZ |
| Hydrant and Access approval | Cleared | 3/13/2024 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 4/19/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 5/2/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/23/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 8/23/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/16/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/16/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/16/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 10/16/2024 | Corrections Issued | JACK KARGODORIAN |
| MERV13>=Rough | 10/16/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 10/16/2024 | Corrections Issued | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 10/16/2024 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 10/16/2024 | Corrections Issued | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 10/30/2024 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 10/30/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/31/2024 | No Access for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/31/2024 | No Access for Inspection | VINCENT HANLEY |
| Green Building Rough | 10/31/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 10/31/2024 | No Access for Inspection | VINCENT HANLEY |
| MERV13>=Rough | 10/31/2024 | No Access for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 10/31/2024 | No Access for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 10/31/2024 | No Access for Inspection | VINCENT HANLEY |
| Wood Frame | 10/31/2024 | No Access for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/8/2024 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 11/8/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 11/8/2024 | Partial Approval | VINCENT HANLEY |
| MERV13>=Rough | 11/8/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 11/8/2024 | Corrections Issued | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/8/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/25/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/25/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Rough | 11/25/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 11/25/2024 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 11/25/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/25/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/9/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/9/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/9/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/13/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Partial Approval | VINCENT HANLEY |
| Insulation | 1/13/2025 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/13/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 1/13/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/13/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/21/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/21/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/21/2025 | Approved | VINCENT HANLEY |
| Insulation | 1/21/2025 | Approved | VINCENT HANLEY |
| Final | 6/23/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/23/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 6/23/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 6/23/2025 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 6/23/2025 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Not Ready | WILLIAM WREN |
| ELECTRICAL-Final | 10/21/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 10/21/2025 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Final | 10/21/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 10/21/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Final | 10/21/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2025 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 10/21/2025 | Partial Approval | VINCENT HANLEY |
| Smoke Detectors | 10/21/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/14/2026 | Approved | VINCENT HANLEY |
| Final | 1/14/2026 | OK to Issue CofO | VINCENT HANLEY |
| MERV13>=Final | 1/14/2026 | Approved | VINCENT HANLEY |
| Service/Power Release | 1/14/2026 | Approved | VINCENT HANLEY |