14178 W SAYRE ST 91342

Certificate Information: 14178 W SAYRE ST 91342

Application / Permit
23010-20000-01698
Plan Check / Job No.
B23VN05049
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 20'-0" X 31'-6" TWO STORY BUILDING WITH ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ON SECOND FLOOR AND RECROOM ON FIRST FLOOR ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/19/2024
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/18/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/19/2023 OMID HEDAYAT
Applicant returned to address corrections 8/22/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 9/27/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/8/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 4/4/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 4/15/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/17/2024 SEWADA ZADOORAN MILAGARDI
Issued 4/19/2024 APPLICANT
CofO in Progress 5/21/2025 KEVIN BERBERYAN
CofO in Progress 5/21/2025 KEVIN BERBERYAN
CofO in Progress 10/6/2025 KEVIN BERBERYAN
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/17/2024 CARLOS AGUILERA
Sewer availability Cleared 1/18/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 3/5/2024 LUIS CRUZ
Eng Process Fee Ord 176,300 Cleared 4/1/2024 ROSE MARIE SMITH
Roof/Waste drainage to street Cleared 4/11/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yanez,, Manuel S; Lic. No.: C63467 1089 SANTIAGO DR      CALEXICO, CA 92231

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/5/2024 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 8/13/2024 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 8/26/2024 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 8/28/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 8/29/2024 Partial Inspection ROBERT GOLD
Footing/Foundation/Slab 8/30/2024 Conditional Approval ROBERT GOLD
Wood Frame 10/16/2024 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 11/1/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 11/1/2024 Approved KEVIN BERBERYAN
Wood Frame 11/1/2024 Approved KEVIN BERBERYAN
Insulation 11/12/2024 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 11/12/2024 Corrections Issued KEVIN BERBERYAN
Insulation 11/22/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/22/2024 Approved KEVIN BERBERYAN
Drywall Nailing 12/10/2024 Approved KEVIN BERBERYAN
HVAC-Rough 12/10/2024 Approved KEVIN BERBERYAN
Service/Power Release 4/10/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 4/17/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 4/23/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 4/23/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 4/23/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 4/23/2025 Approved KEVIN BERBERYAN
HVAC-Final 4/23/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Final 4/23/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 4/23/2025 Partial Inspection KEVIN BERBERYAN
Smoke Detectors 4/23/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 5/20/2025 Corrections Issued KEVIN BERBERYAN
Service/Power Release 5/20/2025 Not Required KEVIN BERBERYAN
Smoke Detectors 5/20/2025 Approved KEVIN BERBERYAN
Final 5/21/2025 Corrections Issued KEVIN BERBERYAN
Final 10/6/2025 OK to Issue CofO KEVIN BERBERYAN