1022 N GALLOWAY ST 90272
Certificate Information: 1022 N GALLOWAY ST 90272
- Application / Permit
- 23010-20000-01691
- Plan Check / Job No.
- B23VN05031
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY (30'-0"x77'-0"), 3103 SQFT SINGLE FAMILY DWELLING W/ COVERED PORCH (44 SQFT) AND COVERED DECK (68 SQFT), W/ATTACHED 2 CAR GARAGE (348 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT. ALL ELECTRIC BUILDING
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- Current Status
- CofO Issued on 3/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | PETER MOSESIAN |
| Corrections Issued | 5/6/2023 | PETER MOSESIAN |
| Quality Review Completed | 5/11/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 5/15/2023 | APPLICANT |
| Plan Check Approved | 1/25/2024 | PETER MOSESIAN |
| Issued | 2/1/2024 | APPLICANT |
| CofO in Progress | 3/25/2026 | TEMISTOCLES CAAL |
| Permit Finaled | 3/25/2026 | RICHARD STEINBACH |
| CofO Issued | 3/25/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/25/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 5/11/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2023 | JASON NG |
| Sewer availability | Cleared | 5/15/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 5/26/2023 | KURT CORRAL |
| Trees in Parkway | Cleared | 6/14/2023 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 10/17/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/19/2023 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
| Engineer | Zhao,, Xiaoming; Lic. No.: C70068 | 13402 PARK DR CERRITOS, CA 90703 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2024 | Partial Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/19/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/19/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/27/2024 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 3/28/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 5/7/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/14/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 5/14/2024 | Approved | ARAM AVEDISIAN |
| Sewer | 5/20/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 5/21/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/29/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Green Building Rough | 5/29/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/29/2024 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 5/29/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 5/31/2024 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 5/31/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 6/3/2024 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 6/5/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/7/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/10/2024 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 10/2/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/23/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 11/6/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/6/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 11/13/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/13/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 11/15/2024 | Approved | JESUS RODRIGUEZ |
| Final | 11/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 11/19/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Not Required | JESUS RODRIGUEZ |
| Service/Power Release | 11/19/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 11/19/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/3/2025 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/3/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 7/3/2025 | Corrections Issued | KENNETH NAGLE |
| Underground Mechanical | 7/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/8/2025 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 7/8/2025 | Partial Approval | BOBBY KEY |
| Sewer | 7/11/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/15/2025 | Approved | STEPHANIE SWANSON |
| Sewer | 7/15/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/12/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 9/12/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/19/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/23/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/24/2025 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 10/10/2025 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 10/24/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/19/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/24/2026 | Approved | TEMISTOCLES CAAL |
| Final | 3/24/2026 | OK to Issue CofO | TEMISTOCLES CAAL |