544 N MARTEL AVE 90036
Certificate Information: 544 N MARTEL AVE 90036
- Application / Permit
- 23010-20000-01675
- Plan Check / Job No.
- B23VN04994
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 16' X 40'-1" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA 132D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | RAPHAEL ROSAS |
| Corrections Issued | 4/24/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 4/27/2023 | STEVEN KIM |
| Building Plans Picked Up | 5/1/2023 | APPLICANT |
| Applicant returned to address corrections | 7/11/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 8/4/2023 | RAPHAEL ROSAS |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 5/14/2024 | AMIR NAZARIAN |
| CofO Issued | 5/22/2024 | DEROLD HAUFF |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 5/4/2023 | DANIEL CORONADO |
| Trees in Parkway | Cleared | 5/17/2023 | ADALBERTO VERA |
| Address approval | Cleared | 6/2/2023 | ANA SORIANO |
| Permit | Cleared | 6/2/2023 | ANA SORIANO |
| Hydrant and Access approval | Cleared | 6/5/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2023 | ANA SORIANO |
| Sewer availability | Cleared | 6/20/2023 | ANA SORIANO |
| Low Impact Development (LID) | Cleared | 7/28/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 8/1/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 8/15/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 8/15/2023 | Partial Approval | LILIANA PORTILLO |
| Sewer | 8/15/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 8/15/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Subgrade | 8/17/2023 | Approved | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 9/12/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/12/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Barrier | 9/12/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 9/19/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/19/2023 | Approved | LILIANA PORTILLO |
| METHANE-Barrier | 9/19/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Deputy Wood Construction | 11/14/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 11/21/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/1/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 12/1/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/6/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Approved | LILIANA PORTILLO |
| METHANE-Rough | 12/6/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 12/6/2023 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 12/6/2023 | Approved | LILIANA PORTILLO |
| Insulation | 12/12/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/12/2023 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 12/18/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 12/18/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/18/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 4/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 4/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 4/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 4/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 4/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/24/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 4/24/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 4/24/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Final | 4/24/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Final | 4/24/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Required | AMIR NAZARIAN |
| Service/Power Release | 4/24/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 5/7/2024 | Approved | AMIR NAZARIAN |
| Final | 5/7/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 5/7/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 5/7/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Final | 5/7/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 5/7/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 5/7/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 5/13/2024 | Approved | AMIR NAZARIAN |
| Final | 5/13/2024 | OK to Issue CofO | AMIR NAZARIAN |
| HVAC-Final | 5/13/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Final | 5/13/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 5/13/2024 | Approved | AMIR NAZARIAN |