11586 1/2 W CUMPSTON ST 91601
Certificate Information: 11586 1/2 W CUMPSTON ST 91601
- Application / Permit
- 23010-20000-01671
- Plan Check / Job No.
- B23VN04988
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED 23'-0" x 22'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) PER ENGINEERING
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Current Status
- CofO in Progress on 12/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2023 | ALFRED RAMIREZ |
| Corrections Issued | 5/4/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 6/8/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 7/12/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 10/13/2023 | ALFRED RAMIREZ |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 11/27/2024 | CHRISTOPHER ROJAS |
| No Progress | 12/5/2024 | JUAN VALENZUELA |
| CofO in Progress | 12/5/2024 | JUAN VALENZUELA |
| CofO in Progress | 12/6/2024 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2023 | HUGO LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/4/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 6/4/2023 | HUGO LOPEZ |
| Low Impact Development (LID) | Cleared | 10/9/2023 | TOMMY YIN |
Contact Information
| Contractor | J & J General Construction Inc; Lic. No.: 1067429-B | , |
| Engineer | Jalalpour,, Mohammad; Lic. No.: S6696 | 152 DEERFIELD AVE IRVINE, CA 92606 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 1/29/2024 | Partial Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 2/1/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/27/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 4/5/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/26/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/13/2024 | Partial Approval | SALVADOR MARTINEZ |
| Underground Mechanical | 6/20/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/5/2024 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/5/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/5/2024 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/5/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/11/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| MERV13>=Rough | 7/11/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/11/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 9/30/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 10/8/2024 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 11/13/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| MERV13>=Final | 11/13/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/13/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 11/13/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/13/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 11/26/2024 | Conditional Approval | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 11/26/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 12/6/2024 | Corrections Issued | CHRISTOPHER ROJAS |