19626 W ROSITA ST 91356

Certificate Information: 19626 W ROSITA ST 91356

Application / Permit
23010-20000-01658
Plan Check / Job No.
B23VN04909
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New detach accessory dwelling unit per ordinance
Permit Issued
Issued on 5/1/2024
Issuing Office
Current Status
CofO Issued on 9/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2023 APPLICANT
Assigned to Plan Check Engineer 4/24/2023 WEIJIAN HUANG
Corrections Issued 4/25/2023 WEIJIAN HUANG
Applicant returned to address corrections 1/19/2024 ZAW HAN
Applicant returned to address corrections 3/14/2024 ZAW HAN
Plan Check Approved 4/30/2024 ADAM HEGAZI
Issued 5/1/2024 APPLICANT
CofO in Progress 7/14/2025 JOHN KIDWELL
Permit Finaled 9/8/2025 JOHN JANSON
Permit Finaled 9/8/2025 JOHN JANSON
CofO Issued 9/8/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/4/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/18/2023 MEGAN GODINEZ
Low Impact Development (LID) Cleared 10/25/2023 ERNEST TSE
BHO/Hillside ordinance Cleared 11/7/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 11/7/2023 LEE GUILBEAUX
Sewer availability Cleared 11/7/2023 COLIN LOREDO
Hydrant and Access approval Cleared 12/23/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 7270 HILLSIDE AVE   APT 306    LOS ANGELES, CA 90046

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/6/2024 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 9/9/2024 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 9/12/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/23/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/4/2025 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 2/4/2025 Partial Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 2/4/2025 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 2/7/2025 Partial Approval SCOTT SOBEL
Shower Pan 2/7/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 2/10/2025 Partial Approval JOHN KIDWELL
PLUMBING-Rough 2/10/2025 Approved JOHN KIDWELL
ELECTRICAL-Rough 2/18/2025 Approved JOHN KIDWELL
HVAC-Rough 2/21/2025 Approved JOHN KIDWELL
Insulation 2/26/2025 Conditional Approval JOHN KIDWELL
Drywall Nailing 3/7/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 4/16/2025 Approved JOHN KIDWELL
HVAC-Final 4/16/2025 Approved JOHN KIDWELL
PLUMBING-Final 4/16/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/5/2025 Approved JOHN KIDWELL
Final 5/5/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Approved JOHN KIDWELL
Service/Power Release 5/5/2025 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 5/5/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 5/5/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 5/9/2025 Approved JOHN KIDWELL
ELECTRICAL-Rough 5/9/2025 Approved JOHN KIDWELL
Final 5/19/2025 Partial Inspection JOHN KIDWELL
Service/Power Release 5/19/2025 Not Ready for Inspection JOHN KIDWELL
Final 5/21/2025 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 5/21/2025 Approved JOHN KIDWELL
Final 6/20/2025 OK to Issue CofO JOHN KIDWELL