9315 N WISH AVE 91325

Certificate Information: 9315 N WISH AVE 91325

Application / Permit
23010-20000-01655
Plan Check / Job No.
B23VN04906
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED 24'-0" x 21'-6" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) AND WITH (N) ATTACHED 24'-0" x 9'-0" PATIO COVER. ALL WORK PER ENG DESIGN
Permit Issued
Issued on 6/25/2024
Issuing Office
Current Status
CofO Issued on 5/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2023 APPLICANT
Assigned to Plan Check Engineer 4/21/2023 ALFRED RAMIREZ
Corrections Issued 4/22/2023 ALFRED RAMIREZ
Applicant returned to address corrections 7/12/2023 ALFRED RAMIREZ
Applicant returned to address corrections 4/1/2024 ALFRED RAMIREZ
Plan Check Approved 6/23/2024 LUISANGEL VALENZUELA
Issued 6/25/2024 APPLICANT
CofO in Progress 4/16/2026 MISAEL ESPARZA
CofO Issued 5/7/2026 RUBEN SALAS
Permit Finaled 5/7/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/26/2023 COLIN LOREDO
BHO/Hillside ordinance Cleared 10/26/2023 COLIN LOREDO
BHO/Hillside ordinance Cleared 10/26/2023 COLIN LOREDO
BHO/Hillside ordinance Cleared 10/26/2023 COLIN LOREDO
BHO/Hillside ordinance Cleared 10/26/2023 COLIN LOREDO
BHO/Hillside ordinance Cleared 10/26/2023 COLIN LOREDO
Sewer availability Cleared 11/8/2023 COLIN LOREDO
Construction near power lines Cleared 1/24/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 3/8/2024 CHARLES POWELL
Low Impact Development (LID) Cleared 3/27/2024 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 4/5/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 4/5/2024 EDGAR ALCARAZ
GPI Written Notices Cleared 6/14/2024 ALFRED RAMIREZ

Contact Information

Architect Mount,, William Thomas; Lic. No.: NA23039       ,
Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/26/2024 Partial Approval JAVIER RAMOS JR
Sewer 8/26/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 8/30/2024 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 8/30/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 10/3/2024 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 10/3/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 10/3/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/3/2024 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 10/3/2024 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 10/7/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 11/20/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 11/20/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/20/2024 Approved JAVIER RAMOS JR
Underground Mechanical 11/20/2024 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 1/7/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 1/14/2025 Partial Approval JAVIER RAMOS JR
Insulation 1/30/2025 Corrections Issued LOUIS ESCOTO
Shower Pan 1/30/2025 Approved LOUIS ESCOTO
Insulation 2/7/2025 Approved LOUIS ESCOTO
Drywall Nailing 2/19/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 2/19/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 11/4/2025 Approved NICHOLAS TROWBRIDGE
Final 11/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Service/Power Release 11/4/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 11/4/2025 Approved NICHOLAS TROWBRIDGE
Final 3/19/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 3/19/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/15/2026 Approved MISAEL ESPARZA
Final 4/15/2026 OK to Issue CofO MISAEL ESPARZA