14876 W RAYMER ST 91405
Certificate Information: 14876 W RAYMER ST 91405
- Application / Permit
- 23010-20000-01639
- Plan Check / Job No.
- B23VN04846
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- NEW THREE (3) STORY SELF-STORAGE FACILITY PER ZA-2022-3811-CU-SPR-WDI.
- Permit Issued
- Issued on 11/27/2024
- Issuing Office
- Metro
- Current Status
- Issued on 11/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | ARMEN JIVALAGIAN |
| Corrections Issued | 5/2/2023 | ARMEN JIVALAGIAN |
| Quality Review Completed | 5/19/2023 | MINYE PAK |
| Applicant returned to address corrections | 7/3/2024 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 9/5/2024 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 9/12/2024 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/17/2024 | ARMEN JIVALAGIAN |
| Plan Check Approved | 10/30/2024 | ARMEN JIVALAGIAN |
| Plan Check Approved | 11/14/2024 | ARMEN JIVALAGIAN |
| Issued | 11/27/2024 | APPLICANT |
Permit Application Clearance Information
| Highway dedication | Cleared | 5/23/2023 | DAGOVERTO GUERRERO |
| Driveway location | Cleared | 6/2/2023 | MIGUEL CRISOSTOMO |
| Internal circulation | Cleared | 6/2/2023 | MIGUEL CRISOSTOMO |
| Address approval | Cleared | 6/14/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2023 | NIKKI ZULUETA |
| Trees in Parkway | Cleared | 8/3/2023 | ADALBERTO VERA |
| Construction near power lines | Cleared | 8/29/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/29/2023 | RIDWAN HARDY |
| DAS Clearance | Cleared | 12/1/2023 | ARMEN JIVALAGIAN |
| Hydrant and Access approval | Cleared | 12/9/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 12/14/2023 | AMMAR ELTAWIL |
| Miscellaneous | Cleared | 1/2/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/2/2024 | LEE GUILBEAUX |
| Permit | Cleared | 1/8/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/9/2024 | CARLOS AGUILERA |
| Prkng lot landscape/Water mgmt | Cleared | 1/16/2024 | DAVID URITA |
| Site Plan review | Cleared | 1/16/2024 | DAVID URITA |
| ZA Case | Cleared | 1/16/2024 | DAVID URITA |
| Green Code | Cleared | 5/15/2024 | ARMEN JIVALAGIAN |
| Metro Rail approval | Cleared | 6/18/2024 | JENNIFER SU |
| Building over 36-ft | Cleared | 7/11/2024 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 9/10/2024 | DANIEL ELIZARRARAS |
Contact Information
| Architect | Jordan,, Bruce Didrik; Lic. No.: C12923 | 131 CALLE IGLESIA SUITE 100 SAN CLEMENTE, CA 92672 |
| Contractor | L T Building Corp; Lic. No.: 1063419-B | , |
| Engineer | Elder,, John; Lic. No.: S6534 | 5181 S EMERALD PL CHANDLER, AZ 85249 |
| Engineer | He,, Liangcai; Lic. No.: GE3033 | 2883 E SPRING ST #300 LONG BEACH, CA 90806 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/10/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 1/23/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/6/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 2/7/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Piling/Pier/Caisson | 2/10/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/12/2025 | Partial Approval | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 2/26/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 2/27/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 2/27/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/27/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/28/2025 | Partial Approval | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/11/2025 | Partial Approval | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/19/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/7/2025 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 4/10/2025 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 4/25/2025 | Conditional Approval | JOHN KITCKO |
| Posting Pre-Inspection | 4/25/2025 | Partial Inspection | JOHN KITCKO |
| Green Building Rough | 4/28/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/28/2025 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/28/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 4/29/2025 | Approved | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 4/29/2025 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 4/30/2025 | Conditional Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/1/2025 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/2/2025 | Approved | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/5/2025 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/8/2025 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/9/2025 | Approved | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/9/2025 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/15/2025 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/19/2025 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/20/2025 | Not Ready for Inspection | GREGORY POMISH |
| Masonry Wall/Backfill | 5/23/2025 | Partial Approval | JOHN KITCKO |
| Masonry Wall/Backfill | 5/27/2025 | Partial Approval | GREGORY POMISH |
| Light Gage Steel Frame | 6/16/2025 | Partial Approval | JOHN KITCKO |
| Structural Steel Frame | 6/16/2025 | Partial Approval | JOHN KITCKO |
| Structural Steel Frame | 6/18/2025 | Partial Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 6/23/2025 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 7/10/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 7/28/2025 | Partial Approval | JOHN KITCKO |
| Insulation | 7/29/2025 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 8/7/2025 | Partial Approval | GREGORY POMISH |
| Light Gage Steel Frame | 8/11/2025 | Not Ready for Inspection | JOHN KITCKO |
| Structural Steel Frame | 8/11/2025 | Not Ready for Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 8/13/2025 | Partial Inspection | JOHN KITCKO |
| Structural Steel Frame | 8/13/2025 | Partial Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 8/15/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Structural Steel Frame | 8/22/2025 | Partial Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 8/25/2025 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Concrete | 8/26/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 8/27/2025 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 9/2/2025 | Partial Approval | DEANDRE HOFFMAN |
| Masonry Wall/Backfill | 9/4/2025 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 9/5/2025 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 9/8/2025 | Partial Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 9/12/2025 | Partial Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 9/15/2025 | Partial Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 10/8/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Not Ready for Inspection | GREGORY POMISH |
| Drywall Nailing | 10/24/2025 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Partial Inspection | ANDREW DORSO |
| Insulation | 10/24/2025 | Partial Inspection | ANDREW DORSO |
| Structural Steel Frame | 10/24/2025 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 10/31/2025 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 11/3/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 11/12/2025 | Partial Approval | KENNETH ROBERTS |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 11/18/2025 | Partial Approval | JOHN KITCKO |
| Structural Steel Frame | 11/21/2025 | Not Ready for Inspection | GREGORY POMISH |
| Structural Steel Frame | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| Interior/Exterior Lathing | 12/2/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 12/10/2025 | Partial Approval | DEANDRE HOFFMAN |
| Special/Order Compliance | 12/10/2025 | Corrections Issued | DEANDRE HOFFMAN |
| Drywall Nailing | 12/18/2025 | Partial Approval | JOHN KITCKO |
| Light Gage Steel Frame | 12/18/2025 | Corrections Issued | JOHN KITCKO |
| Structural Steel Frame | 1/5/2026 | Partial Inspection | GREGORY POMISH |
| Drywall Nailing | 2/18/2026 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 2/19/2026 | Partial Inspection | JOHN KITCKO |
| Piling/Pier/Caisson | 4/7/2026 | Partial Approval | JOHN KITCKO |