12651 W WELBY WAY 91606

Certificate Information: 12651 W WELBY WAY 91606

Application / Permit
23010-20000-01637
Plan Check / Job No.
B23VN04838
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan New 2-Story Detached Accessory Dwelling Unit ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
Permit Issued
Issued on 12/19/2023
Issuing Office
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 SUNMIN LEE
Corrections Issued 5/11/2023 SUNMIN LEE
Quality Review Completed 5/12/2023 GARO TELMI
Applicant returned to address corrections 11/20/2023 SUNMIN LEE
Applicant returned to address corrections 12/7/2023 SUNMIN LEE
Plan Check Approved 12/14/2023 SUNMIN LEE
Issued 12/19/2023 APPLICANT
CofO in Progress 11/19/2024 OGANES TARAKHCHYAN
Permit Finaled 12/10/2024 RUBEN SALAS
CofO Issued 12/10/2024 RUBEN SALAS
Permit Finaled 12/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/15/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/17/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 5/17/2023 DAGOVERTO GUERRERO
Construction within easement Cleared 8/9/2023 WALTER RAMIREZ
Low Impact Development (LID) Cleared 10/24/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/30/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/27/2023 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/24/2024 Approved JOSE AVILA
Footing/Foundation/Slab 1/24/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 1/31/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval KIRK SANDERS
Insulation 2/12/2024 Partial Approval KIRK SANDERS
Deputy Wood Construction 2/14/2024 Conditional Approval JOSE AVILA
Wood Frame 2/20/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 3/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/1/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/1/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/1/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 4/1/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 4/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 4/3/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/3/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 4/12/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 4/22/2024 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 4/24/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/24/2024 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 4/30/2024 Partial Approval JUAN VALENZUELA
Sewer 5/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/7/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/7/2024 Approved ROBERTO PALACIOS-LOPEZ
Sewer 5/14/2024 Approved JOSE AVILA
Interior/Exterior Lathing 6/17/2024 Approved MATTHEW NELSON
Drywall Nailing 10/8/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/8/2024 Corrections Issued JENNIFER RABUCHIN
Final 10/8/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/8/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 10/8/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 10/8/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 10/8/2024 Approved JENNIFER RABUCHIN
Final 10/29/2024 No Access for Inspection OGANES TARAKHCHYAN
Final 10/31/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Service/Power Release 10/31/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 11/4/2024 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 11/4/2024 Approved OGANES TARAKHCHYAN
Service/Power Release 12/3/2024 Approved OGANES TARAKHCHYAN