12651 W WELBY WAY 91606
Certificate Information: 12651 W WELBY WAY 91606
- Application / Permit
- 23010-20000-01637
- Plan Check / Job No.
- B23VN04838
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan New 2-Story Detached Accessory Dwelling Unit ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 12/19/2023
- Issuing Office
- Current Status
- CofO Issued on 12/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | SUNMIN LEE |
| Corrections Issued | 5/11/2023 | SUNMIN LEE |
| Quality Review Completed | 5/12/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/20/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 12/7/2023 | SUNMIN LEE |
| Plan Check Approved | 12/14/2023 | SUNMIN LEE |
| Issued | 12/19/2023 | APPLICANT |
| CofO in Progress | 11/19/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 12/10/2024 | RUBEN SALAS |
| CofO Issued | 12/10/2024 | RUBEN SALAS |
| Permit Finaled | 12/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/17/2023 | DAGOVERTO GUERRERO |
| Construction within easement | Cleared | 8/9/2023 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 10/24/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 10/30/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/27/2023 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 1/24/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 1/31/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 2/12/2024 | Partial Approval | KIRK SANDERS |
| Deputy Wood Construction | 2/14/2024 | Conditional Approval | JOSE AVILA |
| Wood Frame | 2/20/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 4/1/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 4/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 4/3/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 4/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 4/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 4/12/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 4/22/2024 | Corrections Issued | KEVIN BERBERYAN |
| Drywall Nailing | 4/24/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 4/24/2024 | Corrections Issued | JUAN VALENZUELA |
| Special/Order Compliance | 4/30/2024 | Partial Approval | JUAN VALENZUELA |
| Sewer | 5/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 5/14/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 6/17/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/8/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/8/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/8/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/8/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/8/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/8/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/8/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/29/2024 | No Access for Inspection | OGANES TARAKHCHYAN |
| Final | 10/31/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 10/31/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 11/4/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 11/4/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 12/3/2024 | Approved | OGANES TARAKHCHYAN |