10512 N ANDORA AVE 91311

Certificate Information: 10512 N ANDORA AVE 91311

Application / Permit
23010-20000-01605
Plan Check / Job No.
B23VN04751
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 8/26/2025
Issuing Office
Current Status
Issued on 8/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 CARLOS MONTES
Corrections Issued 5/17/2023 CARLOS MONTES
Quality Review Completed 5/17/2023 GARO TELMI
Applicant returned to address corrections 8/4/2023 CARLOS MONTES
Plan Check Approved 8/21/2025 CARLOS MONTES
Issued 8/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/20/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/20/2023 MEGAN GODINEZ
Grading Pre-Inspection Cleared 7/10/2023 SERGIO VALENZUELA
Low Impact Development (LID) Cleared 8/21/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 8/24/2023 MEGAN GODINEZ
Sewer availability Cleared 7/19/2025 BRYAN GODINEZ
Private sewage disp. approval Cleared 7/25/2025 DAN RYAN EVANGELISTA
GPI Written Notices Cleared 8/21/2025 CARLOS MONTES

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Pre-Inspection 6/12/2026   
BUILDING-Rough-Frame 6/12/2026   
Green Building Rough 6/12/2026   
PLUMBING-Rough 6/12/2026   
ELECTRICAL-Rough 6/12/2026   
HVAC-Rough 6/12/2026   
Verify Sprinkler Sign Off 6/12/2026   

Inspection Request History

Footing/Foundation/Slab 1/26/2026 Approved JEFFREY HARTLINE
Special/Order Compliance 3/18/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 4/13/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 5/15/2026 Partial Approval JEFFREY HARTLINE