843-843 1/2 E 33RD ST 90011
Certificate Information: 843-843 1/2 E 33RD ST 90011
- Application / Permit
- 23010-20000-01603
- Plan Check / Job No.
- B23VN04743
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *eplan* NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | TSE MING HUANG |
| Corrections Issued | 4/25/2023 | TSE MING HUANG |
| Quality Review Completed | 4/26/2023 | EUGENE BARBEAU |
| Plan Check Approved | 8/4/2023 | TSE MING HUANG |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 4/5/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
| CofO Issued | 4/16/2024 | DEROLD HAUFF |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 5/3/2023 | DALIA MOKAYED |
| Trees in Parkway | Cleared | 5/22/2023 | ADALBERTO VERA |
| Address approval | Cleared | 5/26/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 5/26/2023 | KURT CORRAL |
| Permit | Cleared | 5/26/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/30/2023 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 6/5/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/5/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/7/2023 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/7/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 12/8/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 12/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Conditional Approval | BRENDAN MORELLI |
| HVAC-Rough | 1/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 1/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/29/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/12/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/18/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/4/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 4/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/4/2024 | Approved | ALEJANDRO DE ARTOLA |