14134 W CALIFA ST 91401
Certificate Information: 14134 W CALIFA ST 91401
- Application / Permit
- 23010-20000-01601
- Plan Check / Job No.
- B23VN04737
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY (21'-0"x31'-0"), 1170 SQFT SINGLE FAMILY DWELLING W/NFP A 13D SPRINKLERS THROUGHOUT PER SB9
- Permit Issued
- Issued on 11/15/2023
- Issuing Office
- Current Status
- Issued on 11/15/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | PETER MOSESIAN |
| Corrections Issued | 4/24/2023 | PETER MOSESIAN |
| Quality Review Completed | 4/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 4/28/2023 | APPLICANT |
| Plan Check Approved | 11/15/2023 | PETER MOSESIAN |
| Issued | 11/15/2023 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/10/2023 | MATTHEW CRAIG |
| Address approval | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 9/22/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/29/2023 | NIKKI ZULUETA |
| Senate Bill 9 | Cleared | 10/11/2023 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/8/2026 |
Inspection Request History
| PLUMBING-Rough | 1/19/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 1/26/2024 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/26/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/20/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/10/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 9/10/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 9/10/2024 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 9/10/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/12/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/17/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 10/1/2024 | Corrections Issued | LOUIS ESCOTO |
| Shower Pan | 10/18/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/30/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/30/2024 | Approved | RYAN SALAZAR |
| Sewer | 10/30/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 6/18/2025 | Approved | RYAN SALAZAR |
| Final | 9/9/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 9/9/2025 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 9/9/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 9/9/2025 | Approved | RYAN SALAZAR |
| Final | 1/14/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/14/2026 | Approved | VINCENT HANLEY |
| Service/Power Release | 1/14/2026 | Corrections Issued | VINCENT HANLEY |
| Final | 1/23/2026 | Partial Approval | RYAN SALAZAR |
| Service/Power Release | 1/23/2026 | Approved | RYAN SALAZAR |