6330 N BLUEBELL AVE 91606

Certificate Information: 6330 N BLUEBELL AVE 91606

Application / Permit
23010-20000-01568
Plan Check / Job No.
B23VN04646
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan REMODEL (E) SFD AND Construction of addition (280SQFT) to a 1 story single family dwelling, ADDITION COVERRED PATIO (66.5SQFT) AND OVER PORCH AT REAR OF (E) SFD
Permit Issued
Issued on 5/8/2023
Issuing Office
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2023 APPLICANT
Assigned to Plan Check Engineer 4/19/2023 KHUONG TRUONG
Corrections Issued 4/20/2023 KHUONG TRUONG
Plan Check Approved 5/3/2023 KHUONG TRUONG
Issued 5/8/2023 APPLICANT
CofO in Progress 7/23/2025 OGANES TARAKHCHYAN
Permit Finaled 7/30/2025 RUBEN SALAS
CofO Issued 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/26/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/26/2023 LEE GUILBEAUX
Sewer availability Cleared 4/26/2023 LEE GUILBEAUX

Contact Information

Contractor Guerrero Construction Group Inc; Lic. No.: 1037996-B       ,
Engineer Nohroodi,, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/6/2023 Conditional Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 6/9/2023 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 6/9/2023 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 6/20/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/5/2023 Corrections Issued KIRK SANDERS
Underground Mechanical 7/5/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 7/12/2023 Partial Approval KIRK SANDERS
Underground Mechanical 7/12/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Partial Approval KIRK SANDERS
Insulation 7/18/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Corrections Issued KIRK SANDERS
Green Building Rough 7/31/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Approved KIRK SANDERS
HVAC-Rough 8/11/2023 Approved RYAN SALAZAR
Insulation 8/17/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 8/23/2023 Corrections Issued KIRK SANDERS
Gas Test 8/23/2023 Not Ready for Inspection KIRK SANDERS
Green Building Rough 8/23/2023 Not Ready for Inspection KIRK SANDERS
Sewer 8/23/2023 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 8/23/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 8/28/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 8/28/2023 Corrections Issued KIRK SANDERS
Gas Test 8/28/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 8/28/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 8/31/2023 Approved CHRISTOPHER ROJAS
Shower Pan 8/31/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/5/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 9/5/2023 Approved KIRK SANDERS
Green Building Rough 9/5/2023 Approved KIRK SANDERS
Insulation 9/5/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 9/8/2023 Approved KIRK SANDERS
Drywall Nailing 10/4/2023 Approved CHRISTOPHER ROJAS
Final 5/6/2025 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 5/6/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 5/6/2025 Approved OGANES TARAKHCHYAN
Final 7/2/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 7/2/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/18/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 7/18/2025 Approved OGANES TARAKHCHYAN
Final 7/22/2025 OK to Issue CofO OGANES TARAKHCHYAN