633 W 30TH ST 90007

Certificate Information: 633 W 30TH ST 90007

Application / Permit
23010-20000-01482
Plan Check / Job No.
B23VN04393
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: New detached ADU on multi-family lot per 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d)&(g). 1,315 SF floor area.
Permit Issued
Issued on 11/3/2023
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 ARSALAN SHABESTARI
Corrections Issued 4/15/2023 ARSALAN SHABESTARI
Quality Review Completed 4/20/2023 GARO TELMI
Plan Check Approved 11/2/2023 ARSALAN SHABESTARI
Issued 11/3/2023 APPLICANT
CofO in Progress 12/10/2025 ALEJANDRO DE ARTOLA
Permit Finaled 12/12/2025 DEROLD HAUFF
CofO Issued 12/12/2025 DEROLD HAUFF
Permit Finaled 12/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Historic Resource Verification Cleared 4/24/2023 MAX LODER
ZA Case Cleared 4/24/2023 DALIA MOKAYED
ZI Cleared 4/24/2023 DALIA MOKAYED
Redevelopment Project Area Cleared 5/4/2023 GRACIELA ACOSTA
Address approval Cleared 5/24/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 5/25/2023 ANA SORIANO
Sewer availability Cleared 5/25/2023 ANA SORIANO
Construction near power lines Cleared 9/16/2023 RIDWAN HARDY
Hydrant and Access approval Cleared 9/20/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 9/28/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/12/2023 JEANIE LAM

Contact Information

Architect Badie,, Amin; Lic. No.: NA28846       ,
Contractor A M S Construction; Lic. No.: 992388-B       ,
Contractor Jax J C C Inc; Lic. No.: 992388-B       ,
Engineer Sadeghi,, Hamid M; Lic. No.: NA33504       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/14/2023 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 3/29/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 3/29/2024 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 4/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/10/2024 Partial Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/17/2024 Partial Approval ALEJANDRO DE ARTOLA
METHANE-Rough 4/25/2024 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/30/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/30/2024 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 4/30/2024 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 4/30/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 6/21/2024 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 6/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 6/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/28/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 6/28/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/28/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/29/2024 Not Ready for Inspection HERBERT GIRON
MERV13>=Rough 6/29/2024 Not Ready for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 6/29/2024 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 7/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/3/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 7/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 7/11/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/26/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/30/2024 Approved ALEJANDRO DE ARTOLA
Insulation 7/30/2024 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/30/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 8/2/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/5/2024 Partial Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/11/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 2/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 2/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/27/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 2/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 2/27/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/25/2025 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 8/25/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/25/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/25/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/25/2025 Approved ALEJANDRO DE ARTOLA
Final 11/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Final 11/20/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/20/2025 Approved ALEJANDRO DE ARTOLA
Final 11/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Final 12/10/2025 OK to Issue CofO ALEJANDRO DE ARTOLA