1222 W 52ND ST 90037

Certificate Information: 1222 W 52ND ST 90037

Application / Permit
23010-20000-01475
Plan Check / Job No.
B23VN04346
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 9/22/2023
Issuing Office
Current Status
CofO Issued on 3/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 CARLOS MONTES
Corrections Issued 5/1/2023 CARLOS MONTES
Quality Review Completed 5/5/2023 OMID HEDAYAT
Applicant returned to address corrections 8/16/2023 CARLOS MONTES
Applicant returned to address corrections 9/7/2023 CARLOS MONTES
Plan Check Approved 9/21/2023 CARLOS MONTES
Issued 9/22/2023 APPLICANT
CofO in Progress 3/9/2026 SABAS ALONSO
Permit Finaled 3/9/2026 DEROLD HAUFF
CofO Issued 3/9/2026 DEROLD HAUFF
Permit Finaled 3/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/27/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 5/30/2023 ANA SORIANO
Sewer availability Cleared 5/30/2023 ANA SORIANO
Low Impact Development (LID) Cleared 8/1/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 8/6/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 10/3/2023 Approved SABAS ALONSO
Underground Mechanical 10/3/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 12/4/2023 Not Ready for Inspection CRAIG DAVIS
Green Building Rough 12/4/2023 Not Ready for Inspection CRAIG DAVIS
Verify Sprinkler Sign Off 12/4/2023 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 1/24/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Partial Approval SABAS ALONSO
Green Building Rough 2/6/2024 Corrections Issued SABAS ALONSO
HVAC-Rough 2/6/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 2/6/2024 Partial Approval SABAS ALONSO
PLUMBING-Rough 2/6/2024 Approved SABAS ALONSO
Insulation 2/14/2024 Approved SABAS ALONSO
Drywall Nailing 3/29/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 4/2/2024 No Access for Inspection SABAS ALONSO
Drywall Nailing 4/2/2024 No Access for Inspection SABAS ALONSO
Green Building Rough 4/2/2024 No Access for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 4/2/2024 No Access for Inspection SABAS ALONSO
Drywall Nailing 4/5/2024 Corrections Issued ALIZAH MAYAGOITIA
Drywall Nailing 4/8/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 5/3/2024 No Access for Inspection JOSH MEISTER
Interior/Exterior Lathing 5/10/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 7/18/2024 No Access for Inspection SABAS ALONSO
Final 7/18/2024 No Access for Inspection SABAS ALONSO
Green Building Final 7/18/2024 No Access for Inspection SABAS ALONSO
Green Building Rough 7/18/2024 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 7/18/2024 No Access for Inspection SABAS ALONSO
Smoke Detectors 7/18/2024 No Access for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 7/18/2024 No Access for Inspection SABAS ALONSO
Final 8/1/2024 Corrections Issued SABAS ALONSO
Final 8/5/2024 Corrections Issued SABAS ALONSO
Final 8/26/2024 No Access for Inspection SABAS ALONSO
Sewer 10/4/2024 Approved SABAS ALONSO
Underground Mechanical 10/4/2024 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 10/25/2024 No Access for Inspection CRAIG DAVIS
Final 10/25/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Final 10/25/2024 No Access for Inspection CRAIG DAVIS
Green Building Rough 10/25/2024 No Access for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Not Ready CRAIG DAVIS
Service/Power Release 10/25/2024 Not Ready for Inspection CRAIG DAVIS
Smoke Detectors 10/25/2024 No Access for Inspection CRAIG DAVIS
Verify Sprinkler Sign Off 10/25/2024 No Access for Inspection CRAIG DAVIS
Final 11/1/2024 No Access for Inspection JOSE MACIAS
Smoke Detectors 11/1/2024 No Access for Inspection JOSE MACIAS
Green Building Final 12/19/2025 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/6/2026 Approved SABAS ALONSO
Final 1/6/2026 Corrections Issued SABAS ALONSO
Green Building Final 1/6/2026 Approved SABAS ALONSO
Green Building Rough 1/6/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/6/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 1/6/2026 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 1/6/2026 Approved SABAS ALONSO
Verify Sprinkler Sign Off 1/6/2026 Not Ready for Inspection SABAS ALONSO
Final 3/3/2026 OK to Issue CofO SABAS ALONSO
Gas Test 3/3/2026 Approved SABAS ALONSO
Service/Power Release 3/3/2026 Not Ready for Inspection SABAS ALONSO