631 1/2 W 30TH ST 90007
Certificate Information: 631 1/2 W 30TH ST 90007
- Application / Permit
- 23010-20000-01474
- Plan Check / Job No.
- B23VN04342
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *eplan* NEW DET. 2-STORY ADU PER CA GOVT. CODE 65852.2 (e)(1)(D) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/1/2023
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/22/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 4/27/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 9/11/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 9/13/2023 | MAHNAZ NOURHASHEMI |
| Issued | 10/1/2023 | APPLICANT |
| CofO in Progress | 12/10/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/12/2025 | DEROLD HAUFF |
| CofO Issued | 12/12/2025 | DEROLD HAUFF |
| Permit Finaled | 12/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/2/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 5/4/2023 | GRACIELA ACOSTA |
| Address approval | Cleared | 5/25/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 6/2/2023 | HUGO LOPEZ |
| Hydrant and Access approval | Cleared | 6/29/2023 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 8/24/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/25/2023 | HUGO LOPEZ |
Contact Information
| Architect | Badie,, Amin; Lic. No.: NA28846 | , |
| Contractor | A M S Construction; Lic. No.: 992388-B | , |
| Contractor | Jax J C C Inc; Lic. No.: 992388-B | , |
| Engineer | Sadeghi,, Hamid M; Lic. No.: C33504 | 30941 W AGOURA RD 236 WESTLAKE VILLAGE, CA 91361 |
| Engineer | Sadeghi,, Hamid M; Lic. No.: NA33504 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 3/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 3/22/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 4/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 4/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 4/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 4/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 4/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 4/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 4/30/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 5/20/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 6/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/12/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 6/12/2024 | Approved | SABAS ALONSO |
| MERV13>=Rough | 6/12/2024 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Rough | 6/12/2024 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 6/12/2024 | Approved | SABAS ALONSO |
| METHANE-Rough | 6/14/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 7/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 7/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/20/2024 | Approved | DAVID FEILER |
| Green Building Rough | 7/20/2024 | Approved | DAVID FEILER |
| Insulation | 7/20/2024 | Approved | DAVID FEILER |
| Drywall Nailing | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/6/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 6/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/20/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 6/20/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 6/20/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 6/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 8/19/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/19/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Final | 12/2/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Final | 12/10/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |