631 1/2 W 30TH ST 90007

Certificate Information: 631 1/2 W 30TH ST 90007

Application / Permit
23010-20000-01474
Plan Check / Job No.
B23VN04342
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*eplan* NEW DET. 2-STORY ADU PER CA GOVT. CODE 65852.2 (e)(1)(D) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 10/1/2023
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 MAHNAZ NOURHASHEMI
Corrections Issued 4/22/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 4/27/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/11/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 9/13/2023 MAHNAZ NOURHASHEMI
Issued 10/1/2023 APPLICANT
CofO in Progress 12/10/2025 ALEJANDRO DE ARTOLA
Permit Finaled 12/12/2025 DEROLD HAUFF
CofO Issued 12/12/2025 DEROLD HAUFF
Permit Finaled 12/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Historic Resource Verification Cleared 5/2/2023 MAX LODER
Redevelopment Project Area Cleared 5/4/2023 GRACIELA ACOSTA
Address approval Cleared 5/25/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/2/2023 HUGO LOPEZ
Sewer availability Cleared 6/2/2023 HUGO LOPEZ
Hydrant and Access approval Cleared 6/29/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 8/24/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/25/2023 HUGO LOPEZ

Contact Information

Architect Badie,, Amin; Lic. No.: NA28846       ,
Contractor A M S Construction; Lic. No.: 992388-B       ,
Contractor Jax J C C Inc; Lic. No.: 992388-B       ,
Engineer Sadeghi,, Hamid M; Lic. No.: C33504 30941 W AGOURA RD 236      WESTLAKE VILLAGE, CA 91361
Engineer Sadeghi,, Hamid M; Lic. No.: NA33504       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/12/2023 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 11/13/2023 Not Ready for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 3/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/21/2024 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/21/2024 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 3/22/2024 Conditional Approval ALEJANDRO DE ARTOLA
METHANE-Rough 4/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 4/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Subgrade 4/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/17/2024 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 4/17/2024 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 4/17/2024 Approved ALEJANDRO DE ARTOLA
Deputy Wood Construction 4/30/2024 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/20/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 6/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/4/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/7/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/12/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 6/12/2024 Approved SABAS ALONSO
MERV13>=Rough 6/12/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 6/12/2024 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 6/12/2024 Approved SABAS ALONSO
METHANE-Rough 6/14/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 7/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 7/11/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/20/2024 Approved DAVID FEILER
Green Building Rough 7/20/2024 Approved DAVID FEILER
Insulation 7/20/2024 Approved DAVID FEILER
Drywall Nailing 7/23/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/6/2024 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/30/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 3/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 6/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/20/2025 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Final 6/20/2025 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 6/20/2025 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Final 6/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/26/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 6/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 8/19/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 8/19/2025 Approved ALEJANDRO DE ARTOLA
Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/25/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/25/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/25/2025 Approved ALEJANDRO DE ARTOLA
Final 11/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Final 12/2/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Final 12/10/2025 OK to Issue CofO ALEJANDRO DE ARTOLA