20198-20198 1/2 W LASSEN ST 91311

Certificate Information: 20198-20198 1/2 W LASSEN ST 91311

Application / Permit
23010-20000-01452
Plan Check / Job No.
B23VN04222
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* NEW 2-STORY SFD PER SB 9 TWO-UNIT DEVELOPMENT CA 65852.21 AND ATTACHED ADU PER LAMC 12.22A.33(c) AND (e).
Permit Issued
Issued on 10/24/2023
Issuing Office
Current Status
CofO Issued on 2/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 VIVIAN LAO
Corrections Issued 4/11/2023 VIVIAN LAO
Quality Review Completed 4/11/2023 GARO TELMI
Applicant returned to address corrections 8/7/2023 VIVIAN LAO
Applicant returned to address corrections 8/22/2023 VIVIAN LAO
Plan Check Approved 9/5/2023 VIVIAN LAO
Issued 10/24/2023 APPLICANT
CofO in Progress 6/14/2024 DAVID SCANTLIN
CofO in Progress 6/20/2024 DAVID SCANTLIN
CofO in Progress 6/20/2024 DAVID SCANTLIN
CofO in Progress 7/9/2024 DAVID SCANTLIN
No Progress 1/8/2025 HENRY KIM
CofO in Progress 1/8/2025 HENRY KIM
Permit Finaled 2/9/2026 JOHN JANSON
CofO Issued 2/9/2026 JOHN JANSON
Permit Finaled 2/9/2026 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/16/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 7/7/2023 ANTHONY VARGAS
Senate Bill 9 Cleared 7/11/2023 NATHAN ROMINE
Address approval Cleared 7/12/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 7/13/2023 NIKKI ZULUETA
Sewer availability Cleared 7/17/2023 NIKKI ZULUETA
Watercourse Cleared 7/19/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 8/24/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/9/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 11/15/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval DAVID SCANTLIN
Wood Frame 11/29/2023 Not Ready for Inspection DAVID SCANTLIN
Deputy Wood Construction 12/7/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 12/15/2023 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 12/15/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/17/2024 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 1/29/2024 Approved KRISTEN CAUSEY
HVAC-Rough 1/29/2024 Approved KRISTEN CAUSEY
Insulation 2/8/2024 Approved DAVID SCANTLIN
Wood Frame 2/8/2024 Approved DAVID SCANTLIN
Drywall Nailing 2/16/2024 Approved GEVORK IPCHYAN
Green Building Rough 2/16/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 2/21/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 2/23/2024 Approved DAVID SCANTLIN
Shower Pan 2/23/2024 Approved DAVID SCANTLIN
Sewer 3/11/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 5/17/2024 Approved DAVID SCANTLIN
Final 5/17/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 5/17/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Not Ready DAVID SCANTLIN
Service/Power Release 5/17/2024 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 5/17/2024 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 5/17/2024 Approved DAVID SCANTLIN
Final 6/13/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 6/13/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Approved DAVID SCANTLIN
Service/Power Release 6/13/2024 Approved DAVID SCANTLIN
Final 7/8/2024 OK to Issue CofO DAVID SCANTLIN
Special/Order Compliance 1/2/2025 Corrections Issued DAVID SCANTLIN