13147 W VAUGHN ST 91340
Certificate Information: 13147 W VAUGHN ST 91340
- Application / Permit
- 23010-20000-01451
- Plan Check / Job No.
- B23VN04218
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 1/30/2024
- Issuing Office
- Current Status
- CofO Issued on 12/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | DANIEL YIP |
| Corrections Issued | 4/22/2023 | DANIEL YIP |
| Quality Review Completed | 4/25/2023 | GARO TELMI |
| Plan Check Approved | 1/24/2024 | DANIEL YIP |
| Issued | 1/30/2024 | APPLICANT |
| CofO in Progress | 11/25/2025 | MICHEL ABAJAN |
| Permit Finaled | 12/3/2025 | RUBEN SALAS |
| CofO Issued | 12/3/2025 | RUBEN SALAS |
| Permit Finaled | 12/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 5/11/2023 | BRENNEN OBETO |
| Address approval | Cleared | 5/12/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2023 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 9/7/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/7/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/7/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/7/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/26/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/23/2024 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/7/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 6/18/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/20/2024 | Corrections Issued | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/20/2024 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 9/20/2024 | Partial Approval | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 9/20/2024 | Approved | MICHEL ABAJAN |
| Insulation | 9/26/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 9/26/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 10/3/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/3/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/13/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/7/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/24/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 7/22/2025 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 10/9/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 10/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Service/Power Release | 10/9/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 10/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 10/17/2025 | Approved | MICHEL ABAJAN |
| Final | 10/17/2025 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 10/17/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/17/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 10/17/2025 | Approved | MICHEL ABAJAN |
| Final | 11/24/2025 | OK to Issue CofO | MICHEL ABAJAN |