13147 W VAUGHN ST 91340

Certificate Information: 13147 W VAUGHN ST 91340

Application / Permit
23010-20000-01451
Plan Check / Job No.
B23VN04218
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 1/30/2024
Issuing Office
Current Status
CofO Issued on 12/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 DANIEL YIP
Corrections Issued 4/22/2023 DANIEL YIP
Quality Review Completed 4/25/2023 GARO TELMI
Plan Check Approved 1/24/2024 DANIEL YIP
Issued 1/30/2024 APPLICANT
CofO in Progress 11/25/2025 MICHEL ABAJAN
Permit Finaled 12/3/2025 RUBEN SALAS
CofO Issued 12/3/2025 RUBEN SALAS
Permit Finaled 12/3/2025 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 5/11/2023 BRENNEN OBETO
Address approval Cleared 5/12/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/2/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 9/7/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 9/7/2023 LEE GUILBEAUX
Sewer availability Cleared 9/7/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/7/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/26/2024 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 4/23/2024 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 5/7/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 6/18/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 9/20/2024 Corrections Issued MICHEL ABAJAN
Interior/Exterior Lathing 9/20/2024 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 9/20/2024 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 9/20/2024 Approved MICHEL ABAJAN
Insulation 9/26/2024 Approved JACK KARGODORIAN
Wood Frame 9/26/2024 Approved JACK KARGODORIAN
Drywall Nailing 10/3/2024 Approved MICHEL ABAJAN
Green Building Rough 10/3/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/13/2024 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 3/7/2025 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/24/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/15/2025 Not Ready for Inspection MICHEL ABAJAN
Pre-Inspection 7/22/2025 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 10/9/2025 Approved NICHOLAS TROWBRIDGE
Final 10/9/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/9/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Service/Power Release 10/9/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 10/9/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 10/17/2025 Approved MICHEL ABAJAN
Final 10/17/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 10/17/2025 Approved MICHEL ABAJAN
PLUMBING-Final 10/17/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 10/17/2025 Approved MICHEL ABAJAN
Final 11/24/2025 OK to Issue CofO MICHEL ABAJAN