6951 N WILBUR AVE 91335
Certificate Information: 6951 N WILBUR AVE 91335
- Application / Permit
- 23010-20000-01450
- Plan Check / Job No.
- B23VN04215
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'- x 20' DETACHED GARAGE WITH AN ADDITION OF 22'-6" x 19'-2" (402 S.F ) TO (N) DETACHED (832 S.F ) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- Current Status
- Issued on 8/10/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/11/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/5/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 8/9/2023 | MIROOSH KHACHATOORIAN |
| Issued | 8/10/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2023 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/17/2023 | GABRIEL ROBLES |
| ZI | Cleared | 4/19/2023 | NELSON RODRIGUEZ |
| Construction near power lines | Cleared | 8/2/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 8/7/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Grading Pre-Inspection | 4/17/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Pre-Inspection | 4/17/2025 | Corrections Issued | JUAN ALVARADO |
| Sewer | 4/17/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Pre-Inspection | 5/7/2025 | Partial Inspection | JUAN ALVARADO |
| Underground Mechanical | 5/21/2025 | Partial Approval | JUAN ALVARADO |
| PLUMBING-Rough | 6/4/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Underground Mechanical | 6/9/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 7/24/2025 | Approved | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 8/18/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 9/19/2025 | Corrections Issued | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 9/30/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 9/30/2025 | Approved | JUAN ALVARADO |
| Pre-Inspection | 10/15/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 10/27/2025 | Corrections Issued | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | JUAN ALVARADO |
| Wood Frame | 10/29/2025 | Corrections Issued | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 11/26/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Rough-Elec/Plmb/HVAC | 12/24/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 12/31/2025 | Partial Approval | JUAN ALVARADO |
| ELECTRICAL-Rough | 1/7/2026 | Approved | KRISTEN CAUSEY |
| HVAC-Rough | 1/7/2026 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/7/2026 | Partial Approval | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/7/2026 | Approved | KRISTEN CAUSEY |
| Wood Frame | 1/7/2026 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/24/2026 | Approved | JUAN ALVARADO |
| Green Building Rough | 3/24/2026 | Approved | JUAN ALVARADO |
| Insulation | 3/24/2026 | Approved | JUAN ALVARADO |
| Drywall Nailing | 4/29/2026 | Approved | JUAN ALVARADO |