5847 N VESPER AVE 91411
Certificate Information: 5847 N VESPER AVE 91411
- Application / Permit
- 23010-20000-01440
- Plan Check / Job No.
- B23VN04187
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER CITY OF LOS ANGELES ORDINANCE LAMC 12.22 A.33(c)-(d) . THIS NEW BUILDING IS LOCATED AT THE REAR OF THE LOT. THE ADDITION TO THE FRONT HOUSE IS UNDER SEPARATE PERMIT.
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | QUAN NGHIEM |
| Corrections Issued | 5/2/2023 | QUAN NGHIEM |
| Quality Review Completed | 5/3/2023 | KEN GILL |
| Building Plans Picked Up | 5/5/2023 | APPLICANT |
| Applicant returned to address corrections | 9/11/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 1/24/2024 | QUAN NGHIEM |
| Plan Check Approved | 2/22/2024 | QUAN NGHIEM |
| Issued | 2/22/2024 | APPLICANT |
| CofO in Progress | 1/6/2025 | RYAN SALAZAR |
| CofO in Progress | 1/16/2025 | RYAN SALAZAR |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
| CofO Issued | 2/4/2025 | RUBEN SALAS |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/14/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/28/2023 | RIDWAN HARDY |
| Sewer availability | Cleared | 8/29/2023 | DAGOVERTO GUERRERO |
| Senate Bill 9 | Cleared | 12/28/2023 | NATHAN ROMINE |
| Low Impact Development (LID) | Cleared | 2/21/2024 | ROGELIO CORTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/2/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 4/2/2024 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 5/9/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/21/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/21/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/22/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/22/2024 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 5/22/2024 | Approved | RYAN SALAZAR |
| Insulation | 6/3/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/3/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 6/5/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/11/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 6/11/2024 | Approved | RYAN SALAZAR |
| Final | 12/13/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 12/13/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 12/13/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 12/13/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 12/20/2024 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 12/20/2024 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Final | 12/20/2024 | Approved | RYAN SALAZAR |
| Final | 12/31/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 12/31/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 12/31/2024 | Approved | RYAN SALAZAR |
| Final | 1/15/2025 | OK to Issue CofO | RYAN SALAZAR |