6739 N SUNNY BRAE AVE 91306
Certificate Information: 6739 N SUNNY BRAE AVE 91306
- Application / Permit
- 23010-20000-01422
- Plan Check / Job No.
- B23VN04085
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 4/8/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/12/2023 | APPLICANT |
| Applicant returned to address corrections | 9/20/2023 | JESSE ARELLANO |
| Plan Check Approved | 9/25/2023 | PINANK PATEL |
| Issued | 12/5/2023 | APPLICANT |
| CofO in Progress | 9/12/2024 | ALEXANDER HANDY |
| CofO Issued | 9/27/2024 | JOHN JANSON |
| Permit Finaled | 9/27/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 5/11/2023 | NIKKI ZULUETA |
| ZI | Cleared | 5/19/2023 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 6/23/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 9/7/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/8/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Raul'S Builder; Lic. No.: 1046445-B | 8331 POOLE AVE SUN VALLEY, CA 91352 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/7/2023 | Partial Approval | ALEXANDER HANDY |
| Underground Mechanical | 12/7/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 12/11/2023 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/11/2023 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/13/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 1/4/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 1/4/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 1/4/2024 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Rough | 1/18/2024 | Partial Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 1/18/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 1/18/2024 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 1/18/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 1/23/2024 | Approved | ALEXANDER HANDY |
| Insulation | 1/23/2024 | Conditional Approval | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 1/23/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 1/24/2024 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 1/26/2024 | Partial Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 2/16/2024 | Approved | ARUTYUN MADATYAN |
| Final | 4/3/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 4/3/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 4/3/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 4/3/2024 | Approved | ALEXANDER HANDY |
| Final | 5/7/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/7/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 5/7/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 5/22/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 5/22/2024 | Approved | ALEXANDER HANDY |
| Service/Power Release | 5/22/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Special/Order Compliance | 6/7/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/11/2024 | Approved | ALEXANDER HANDY |
| Final | 9/11/2024 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 9/11/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/11/2024 | Approved | ALEXANDER HANDY |