12458 W GREENE AVE 90066

Certificate Information: 12458 W GREENE AVE 90066

Application / Permit
23010-20000-01410
Plan Check / Job No.
B23VN04071
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR. SHAPED 26'-2 1/2" x 32' ONE-STORY DET. ACCESSORY DWELLING UNIT [PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)] W/ ROOF DECK; NFPA-13D THRU-OUT
Permit Issued
Issued on 3/27/2025
Issuing Office
West Los Angeles
Current Status
Issued on 3/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 SEAN SHAHMIRI
Corrections Issued 4/24/2023 SEAN SHAHMIRI
Quality Review Completed 4/24/2023 OMID HEDAYAT
Building Plans Picked Up 4/26/2023 APPLICANT
Applicant returned to address corrections 9/4/2024 SEAN SHAHMIRI
Applicant returned to address corrections 10/23/2024 SEAN SHAHMIRI
Plan Check Approved 10/23/2024 SEAN SHAHMIRI
Issued 3/27/2025 APPLICANT

Permit Application Clearance Information

Construction within easement Cleared 7/10/2023 RIDWAN HARDY
Hydrant and Access approval Cleared 8/21/2024 LAVEON RIDER
Address approval Cleared 8/29/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/30/2024 DARIN LAM
Sewer availability Cleared 8/30/2024 DARIN LAM
Low Impact Development (LID) Cleared 10/4/2024 ERNEST TSE
Specific Plan Cleared 10/15/2024 FREDDY GARCIA
Roof/Waste drainage to street Cleared 10/23/2024 DARIN LAM

Contact Information

Contractor Zepeda Juan; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/20/2025 Partial Approval RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 6/20/2025 Approved RUBEN RIVAS
Sewer 6/20/2025 Approved RUBEN RIVAS
Underground Mechanical 6/20/2025 Partial Approval RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 7/10/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 7/10/2025 Approved RUBEN RIVAS
Deputy Reinf. Concrete 7/11/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Approved RUBEN RIVAS
ELECTRICAL-Rough 10/31/2025 Approved RUBEN RIVAS
HVAC-Rough 10/31/2025 Approved RUBEN RIVAS
PLUMBING-Rough 10/31/2025 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 11/6/2025 Corrections Issued WILBER ROSALES
Green Building Rough 11/6/2025 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 11/6/2025 Approved WILBER ROSALES
Verify Sprinkler Sign Off 11/6/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 11/20/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/20/2025 Partial Approval STEPHANIE SWANSON
Insulation 12/1/2025 Corrections Issued ANTHONY EGSON
Insulation 12/3/2025 Approved ANTHONY EGSON
Drywall Nailing 12/10/2025 Approved RUBEN RIVAS
Green Building Rough 12/10/2025 Approved RUBEN RIVAS
Shower Pan 1/13/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 1/15/2026 Approved DAKOTA LOW
ELECTRICAL-Final 5/15/2026 Approved MORRIS JACKSON
HVAC-Final 5/15/2026 Approved MORRIS JACKSON
PLUMBING-Final 5/15/2026 Not Ready for Inspection MORRIS JACKSON
Final 5/27/2026 Corrections Issued MORRIS JACKSON
Green Building Final 5/27/2026 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 5/27/2026 SGSOV Approved MORRIS JACKSON
Service/Power Release 5/27/2026 Approved MORRIS JACKSON
Smoke Detectors 5/27/2026 Approved MORRIS JACKSON
Final 6/3/2026 Not Ready for Inspection MORRIS JACKSON