15452 W ROMAR ST 91345

Certificate Information: 15452 W ROMAR ST 91345

Application / Permit
23010-20000-01402
Plan Check / Job No.
B23VN04055
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19'-6" x 24'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER WFPP.
Permit Issued
Issued on 10/20/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/7/2023 JEROME MAGAT PALMA
Corrections Issued 4/8/2023 JEROME MAGAT PALMA
Building Plans Picked Up 4/18/2023 APPLICANT
Plan Check Approved 10/20/2023 ISIS ARGUETA
Issued 10/20/2023 APPLICANT
CofO in Progress 11/26/2024 JENNIFER RABUCHIN
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/17/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 4/17/2023 ROMAN GUTIERREZ
Sewer availability Cleared 4/17/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/21/2023 ROMAN GUTIERREZ
Construction near power lines Cleared 5/26/2023 RIDWAN HARDY
Hydrant and Access approval Cleared 10/17/2023 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/21/2023 Partial Inspection JOHN COLEMAN
PLUMBING-Rough 6/13/2024 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/21/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 6/21/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/1/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 8/1/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/5/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/5/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 8/5/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 8/5/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 8/5/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/5/2024 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/5/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/8/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/8/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 8/8/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/8/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/8/2024 Approved JENNIFER RABUCHIN
Insulation 8/12/2024 Corrections Issued LOUIS ESCOTO
Drywall Nailing 8/16/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/16/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 10/2/2024 Corrections Issued JENNIFER RABUCHIN
Final 10/2/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/2/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 10/2/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 10/2/2024 Approved JENNIFER RABUCHIN
Smoke Detectors 10/2/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/26/2024 Approved JENNIFER RABUCHIN
Final 11/26/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 11/26/2024 Approved JENNIFER RABUCHIN
HVAC-Final 11/26/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/26/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved JENNIFER RABUCHIN