4443 N VAN NOORD AVE 91604

Certificate Information: 4443 N VAN NOORD AVE 91604

Application / Permit
23010-20000-01401
Plan Check / Job No.
B23VN04051
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18' X 42' 1-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/13/2023
Issuing Office
Current Status
CofO Issued on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 RAPHAEL ROSAS
Corrections Issued 4/10/2023 RAPHAEL ROSAS
Quality Review Completed 4/13/2023 STEVEN KIM
Building Plans Picked Up 4/14/2023 APPLICANT
Applicant returned to address corrections 7/7/2023 RAPHAEL ROSAS
Plan Check Approved 7/13/2023 RAPHAEL ROSAS
Issued 7/13/2023 APPLICANT
CofO in Progress 4/12/2024 CHRISTOPHE COCHRAN
Permit Finaled 5/8/2024 RUBEN SALAS
CofO Issued 5/8/2024 RUBEN SALAS
Permit Finaled 5/8/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/19/2023 TOMMY YIN
Address approval Cleared 5/22/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/22/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/24/2023 LEE GUILBEAUX
Sewer availability Cleared 5/24/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 6/30/2023 JOHN CONNEALLY
Construction near power lines Cleared 7/5/2023 WALTER RAMIREZ
ZI Cleared 7/7/2023 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/16/2023 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/22/2023 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 9/29/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 10/5/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 10/5/2023 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/12/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 10/19/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/24/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 10/24/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 10/24/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 10/24/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/30/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/7/2023 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 11/27/2023 Approved CHRISTOPHE COCHRAN
Insulation 11/27/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/30/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/7/2023 Approved JOHN COLEMAN
Final 4/12/2024 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 4/12/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 4/12/2024 Approved CHRISTOPHE COCHRAN
Smoke Detectors 4/12/2024 Approved CHRISTOPHE COCHRAN