17428 W ROSCOE BLVD 91325
Certificate Information: 17428 W ROSCOE BLVD 91325
- Application / Permit
- 23010-20000-01396
- Plan Check / Job No.
- B23VN04025
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21' X 30' 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | RAPHAEL ROSAS |
| Corrections Issued | 4/18/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 4/20/2023 | STEVEN KIM |
| Building Plans Picked Up | 4/21/2023 | APPLICANT |
| Applicant returned to address corrections | 1/22/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 2/5/2024 | RAPHAEL ROSAS |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 10/31/2025 | GAREN HAYRAPETYAN |
| No Progress | 11/21/2025 | JOAQUIN GREENOUGH |
| CofO in Progress | 11/21/2025 | GAREN HAYRAPETYAN |
| CofO in Progress | 2/3/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 2/11/2026 | RUBEN SALAS |
| CofO Issued | 2/11/2026 | RUBEN SALAS |
| Permit Finaled | 2/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 4/27/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 7/14/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/15/2023 | JOHN LIN |
| Construction near power lines | Cleared | 9/13/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/14/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/6/2024 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 5/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/13/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 6/24/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Corrections Issued | RAUL OLAGI |
| Sewer | 7/1/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/1/2024 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 9/19/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/19/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/30/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 9/30/2024 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 9/30/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 9/30/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/30/2024 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 9/30/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/15/2024 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 10/15/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 10/15/2024 | Approved | SALVADOR MARTINEZ |
| Insulation | 11/25/2024 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 11/25/2024 | Approved | LOUIS ESCOTO |
| Shower Pan | 11/25/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 12/9/2024 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 12/9/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/9/2024 | Not Ready for Inspection | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 7/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 7/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 7/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 7/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Service/Power Release | 7/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 7/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/1/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/1/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 10/1/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 10/1/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/1/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/31/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Service/Power Release | 10/31/2025 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 11/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 2/4/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |