4537 N STANSBURY AVE 91423

Certificate Information: 4537 N STANSBURY AVE 91423

Application / Permit
23010-20000-01386
Plan Check / Job No.
B23VN04020
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY 74'-6" X 38' SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE ALL WORK PER ENGINEERING NFPA 13 D REQUIRED THROUGHOUT
Permit Issued
Issued on 8/18/2023
Issuing Office
Current Status
CofO Issued on 7/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/8/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/10/2023 OMID HEDAYAT
Building Plans Picked Up 4/10/2023 APPLICANT
Applicant returned to address corrections 6/28/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/11/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 8/10/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/18/2023 SEWADA ZADOORAN MILAGARDI
Issued 8/18/2023 APPLICANT
CofO in Progress 7/11/2024 MISAEL ESPARZA
Permit Finaled 7/26/2024 RUBEN SALAS
CofO Issued 7/26/2024 RUBEN SALAS
Permit Finaled 7/26/2024 RUBEN SALAS

Permit Application Clearance Information

Trees in Parkway Cleared 5/8/2023 ADALBERTO VERA
ZI Cleared 5/18/2023 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 5/25/2023 KURT CORRAL
Low Impact Development (LID) Cleared 7/5/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 7/7/2023 CARLOS AGUILERA
Permit Cleared 7/7/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/7/2023 CARLOS AGUILERA
Sewer availability Cleared 7/7/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/8/2023 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 9/8/2023 Corrections Issued MISAEL ESPARZA
Underground Mechanical 9/12/2023 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/15/2023 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/15/2023 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 9/18/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 9/20/2023 Approved MISAEL ESPARZA
Deputy Reinf. Concrete 9/21/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Partial Approval MISAEL ESPARZA
Deputy Wood Construction 10/27/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval MISAEL ESPARZA
HVAC-Rough 10/27/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/27/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/30/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 10/30/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Approved MISAEL ESPARZA
Green Building Rough 10/30/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 10/30/2023 Approved MISAEL ESPARZA
MERV13>=Rough 10/30/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 10/30/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 10/30/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/13/2023 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 11/13/2023 Approved MISAEL ESPARZA
Insulation 11/20/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/20/2023 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 11/27/2023 Approved MISAEL ESPARZA
Drywall Nailing 12/1/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 12/1/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 6/11/2024 Corrections Issued MISAEL ESPARZA
Final 6/11/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 6/11/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 6/11/2024 Corrections Issued MISAEL ESPARZA
MERV13>=Final 6/11/2024 Approved MISAEL ESPARZA
PLUMBING-Final 6/11/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Approved MISAEL ESPARZA
Service/Power Release 6/11/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 6/11/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/10/2024 Approved MISAEL ESPARZA
Final 7/10/2024 OK to Issue CofO MISAEL ESPARZA
Green Building Final 7/10/2024 Approved MISAEL ESPARZA
HVAC-Final 7/10/2024 Approved MISAEL ESPARZA
PLUMBING-Final 7/10/2024 Approved MISAEL ESPARZA
Service/Power Release 7/10/2024 Approved MISAEL ESPARZA