6567 W COLGATE AVE 90048
Certificate Information: 6567 W COLGATE AVE 90048
- Application / Permit
- 23010-20000-01366
- Plan Check / Job No.
- B23VN03993
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW DETACHED 1-STORY CARPORT (360 SQFT)
- Permit Issued
- Issued on 10/13/2023
- Issuing Office
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | PETER MOSESIAN |
| Corrections Issued | 4/16/2023 | PETER MOSESIAN |
| Quality Review Completed | 4/21/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 4/21/2023 | APPLICANT |
| Plan Check Approved | 10/13/2023 | PETER MOSESIAN |
| Issued | 10/13/2023 | APPLICANT |
| CofO in Progress | 12/4/2024 | ARAM AVEDISIAN |
| CofO Issued | 12/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/22/2023 | TINA MIRANDA |
| CPC | Cleared | 7/25/2023 | LOUIS ORTEGA |
| ZI | Cleared | 7/25/2023 | LOUIS ORTEGA |
| Low Impact Development (LID) | Cleared | 9/7/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/10/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2023 | Partial Approval | BRENDAN LOONEY |
| METHANE-Barrier | 10/26/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Subgrade | 10/26/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/8/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 11/8/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 11/8/2023 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/9/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| Final | 11/15/2024 | Corrections Issued | MEL KHACHATOURIAN |
| METHANE-Final | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| Final | 12/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 12/3/2024 | OK to Issue CofO | ARAM AVEDISIAN |