11558 W LA MAIDA ST 91601
Certificate Information: 11558 W LA MAIDA ST 91601
- Application / Permit
- 23010-20000-01354
- Plan Check / Job No.
- B23VN03985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ADU PER STATE LAW
- Permit Issued
- Issued on 10/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | JAD BASMA |
| Corrections Issued | 4/26/2023 | JAD BASMA |
| Quality Review Completed | 5/1/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 5/8/2023 | APPLICANT |
| Applicant returned to address corrections | 7/3/2023 | JAD BASMA |
| Plan Check Approved | 7/27/2023 | JAD BASMA |
| Issued | 10/17/2023 | APPLICANT |
| CofO Issued | 8/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/27/2023 | CARLOS AGUILERA |
| Specific Plan | Cleared | 5/3/2023 | CHRISTIAN PEARSON |
| Low Impact Development (LID) | Cleared | 6/23/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/23/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 11/9/2023 | Partial Approval | JOHN COLEMAN |
| Pre-Inspection | 11/9/2023 | Approved | JOHN COLEMAN |
| Underground Mechanical | 11/9/2023 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 11/16/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/26/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 12/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 12/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 12/26/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 12/26/2023 | Approved | KIRK SANDERS |
| Structural Steel Frame | 12/26/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 12/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 12/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/12/2024 | Partial Inspection | CRAIG DAVIS |
| Deputy Wood Construction | 1/12/2024 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 1/12/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 1/12/2024 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 1/12/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | CRAIG DAVIS |
| Sewer | 1/12/2024 | Partial Approval | CRAIG DAVIS |
| Shower Pan | 1/12/2024 | Approved | CRAIG DAVIS |
| Structural Steel Frame | 1/12/2024 | Corrections Issued | CRAIG DAVIS |
| Verify Sprinkler Sign Off | 1/12/2024 | Approved | CRAIG DAVIS |
| Wood Frame | 1/12/2024 | Partial Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 1/17/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 1/17/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Approved | KIRK SANDERS |
| Insulation | 1/17/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 1/31/2024 | Approved | KIRK SANDERS |
| Green Building Rough | 1/31/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/31/2024 | Approved | KIRK SANDERS |
| Insulation | 2/7/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 2/26/2024 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 5/1/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 5/7/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Gas Test | 5/16/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/18/2024 | Conditional Approval | CHRISTOPHER ROJAS |
| Green Building Final | 6/18/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 6/18/2024 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/18/2024 | Approved | CHRISTOPHER ROJAS |