5818 N CRANER AVE 91601

Certificate Information: 5818 N CRANER AVE 91601

Application / Permit
23010-20000-01348
Plan Check / Job No.
B23VN03984
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADU WITH ATTACHED GARAGE PER LAMC 12.22 A.33 (c)-(d) - BLDG SPRINLERED THRU-OUT
Permit Issued
Issued on 9/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 MAHNAZ NOURHASHEMI
Corrections Issued 4/25/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 5/3/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 6/2/2023 APPLICANT
Applicant returned to address corrections 2/14/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 4/24/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 5/24/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 7/25/2024 MAHNAZ NOURHASHEMI
Issued 9/27/2024 APPLICANT
CofO in Progress 3/25/2026 ROBERTO PALACIOS-LOPEZ
CofO Issued 4/9/2026 RUBEN SALAS
Permit Finaled 4/9/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/14/2023 GILBERT URREA
Address approval Cleared 8/4/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/7/2023 CARLOS AGUILERA
Sewer availability Cleared 8/7/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 10/31/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/10/2024 CARLOS AGUILERA
Trees in Parkway Cleared 9/19/2024 DYNL MIRANDA
Permit Cleared 9/20/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 11/21/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/25/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/23/2024 Approved JOSE AVILA
Deputy Wood Construction 1/31/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/12/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 3/20/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/25/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/20/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/29/2025 Partial Approval JAVIER RAMOS JR
HVAC-Rough 5/29/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/29/2025 Partial Approval JAVIER RAMOS JR
Pre-Inspection 5/29/2025 Partial Approval JAVIER RAMOS JR
HVAC-Rough 6/5/2025 Partial Inspection JOSE AVILA
Underground Mechanical 6/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/17/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Pre-Inspection 7/17/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 7/17/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/18/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Insulation 8/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 8/21/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 8/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/4/2025 Approved MICHAEL CORTEZ
Shower Pan 9/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 10/1/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 10/1/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 10/24/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 2/9/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 3/16/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 3/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 3/16/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 3/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/16/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 3/16/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/24/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 3/24/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 3/24/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/24/2026 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 3/24/2026 Approved ROBERTO PALACIOS-LOPEZ