14722 W OTSEGO ST 91403
Certificate Information: 14722 W OTSEGO ST 91403
- Application / Permit
- 23010-20000-01334
- Plan Check / Job No.
- B23VN03943
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 12' X 13' DETACHED COVERED PATIO WITH 13' X 6' BATHROOM (SHOWER ACCESSIBLE FROM OUTSIDE FOR POOL USE)
- Permit Issued
- Issued on 7/21/2023
- Issuing Office
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | SELLA BENYAMIN |
| Corrections Issued | 4/18/2023 | SELLA BENYAMIN |
| Quality Review Completed | 4/20/2023 | STEVEN KIM |
| Building Plans Picked Up | 4/21/2023 | APPLICANT |
| Plan Check Approved | 7/18/2023 | SELLA BENYAMIN |
| Issued | 7/21/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | DAVID MATSON |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
| CofO Issued | 5/2/2024 | RUBEN SALAS |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 5/10/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/7/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 7/18/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/22/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/23/2023 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/23/2023 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 9/14/2023 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 10/12/2023 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 10/12/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 10/12/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 10/12/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/24/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/24/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/24/2023 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 10/27/2023 | Approved | THOMAS FINNILA |
| Wood Frame | 11/1/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/13/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/28/2023 | Partial Approval | THOMAS FINNILA |
| Insulation | 12/1/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 12/12/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 4/24/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 4/24/2024 | Approved | THOMAS FINNILA |
| Final | 4/30/2024 | OK to Issue CofO | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 4/30/2024 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 4/30/2024 | Approved | DAVID MATSON |
| Smoke Detectors | 4/30/2024 | Approved | DAVID MATSON |