10743 W SATICOY ST 91352

Certificate Information: 10743 W SATICOY ST 91352

Application / Permit
23010-20000-01274
Plan Check / Job No.
B23VN03802
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* NEW 2-STORY SFD WITH ATTACHED 1-CAR GARAGE PER SB9 TWO-UNIT DEVELOPMENT CA 65852.21 NFPA 13D
Permit Issued
Issued on 5/17/2024
Issuing Office
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 VIVIAN LAO
Corrections Issued 4/29/2023 SUNMIN LEE
Quality Review Completed 5/3/2023 GARO TELMI
Applicant returned to address corrections 8/16/2023 SUNMIN LEE
Plan Check Approved 9/19/2023 VIVIAN LAO
No Progress 5/9/2024 VIVIAN LAO
Plan Check Approved 5/10/2024 VIVIAN LAO
Issued 5/17/2024 APPLICANT
CofO in Progress 9/2/2025 MATTHEW NELSON
Permit Finaled 9/16/2025 RUBEN SALAS
CofO Issued 9/16/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/10/2023 CARLOS AGUILERA
Permit Cleared 5/10/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/24/2023 CARLOS AGUILERA
Sewer availability Cleared 5/24/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 7/11/2023 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/11/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/26/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 6/26/2024 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/5/2024 Approved MATTHEW NELSON
PLUMBING-Rough 7/5/2024 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/18/2024 Approved MATTHEW NELSON
PLUMBING-Rough 7/18/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 11/22/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 11/22/2024 Approved MATTHEW NELSON
Green Building Rough 11/22/2024 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 11/22/2024 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 11/22/2024 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 11/26/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/20/2024 Corrections Issued MATTHEW NELSON
Green Building Rough 12/20/2024 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 12/20/2024 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 12/27/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 12/27/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/27/2024 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 12/27/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/6/2025 Approved MATTHEW NELSON
Green Building Rough 1/6/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/6/2025 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 1/6/2025 Approved MATTHEW NELSON
Insulation 1/21/2025 Approved LOUIS ESCOTO
Drywall Nailing 1/27/2025 Approved MATTHEW NELSON
Shower Pan 2/20/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/17/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 5/5/2025 Approved NICHOLAS TROWBRIDGE
Final 7/30/2025 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 7/30/2025 Approved MATTHEW NELSON
Green Building Final 7/30/2025 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 7/30/2025 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 7/30/2025 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 8/22/2025 Approved MATTHEW NELSON
Final 8/22/2025 Corrections Issued MATTHEW NELSON
Green Building Final 8/22/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 8/22/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Final 8/22/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Not Required MATTHEW NELSON
Service/Power Release 8/22/2025 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 8/22/2025 Approved MATTHEW NELSON
Final 8/29/2025 OK to Issue CofO MATTHEW NELSON
Green Building Final 8/29/2025 Approved MATTHEW NELSON
HVAC-Final 8/29/2025 Approved MATTHEW NELSON
Service/Power Release 8/29/2025 Approved MATTHEW NELSON