11948 W STRATHERN ST 91605

Certificate Information: 11948 W STRATHERN ST 91605

Application / Permit
23010-20000-01272
Plan Check / Job No.
B23VN03800
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE AND ATTACHED TRELLIS NFPA 13D SPRINKLERED THROUGH OUT per SB9 Two-Unit Development Ca Govt Code 65852.21
Permit Issued
Issued on 10/1/2024
Issuing Office
Current Status
Issued on 10/1/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/27/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 JAD BASMA
Corrections Issued 4/1/2023 JAD BASMA
Quality Review Completed 4/7/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 9/11/2024 JAD BASMA
No Progress 9/11/2024 JAD BASMA
Plan Check Approved 9/11/2024 JAD BASMA
No Progress 9/30/2024 JAD BASMA
Plan Check Approved 9/30/2024 JAD BASMA
Issued 10/1/2024 APPLICANT

Permit Application Clearance Information

Highway dedication Cleared 4/14/2023 CARLOS AGUILERA
DAS Clearance Cleared 5/26/2023 JAD BASMA
Hydrant and Access approval Cleared 10/23/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 1/29/2024 LUIS LUVANO
Clean Up Green Up Cleared 1/30/2024 RYAN LY
Address approval Cleared 1/31/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/31/2024 CARLOS AGUILERA
Sewer availability Cleared 2/1/2024 CARLOS AGUILERA
Highway dedication Cleared 2/5/2024 LEE GUILBEAUX
Senate Bill 9 Cleared 2/5/2024 DALIA MOKAYED
Permit Cleared 4/8/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/8/2024 CARLOS AGUILERA
Trees in Parkway Cleared 8/2/2024 DYNL MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/15/2024 Corrections Issued MATTHEW NELSON
Underground Mechanical 10/15/2024 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 10/16/2024 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 10/29/2024 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 1/24/2025 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Partial Approval MATTHEW NELSON
Green Building Rough 1/24/2025 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 1/24/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 2/12/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 2/12/2025 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 2/12/2025 Not Ready for Inspection MATTHEW NELSON
Wood Frame 2/12/2025 Partial Approval MATTHEW NELSON
PLUMBING-Rough 3/3/2025 Approved MATTHEW NELSON
HVAC-Rough 3/12/2025 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 3/19/2025 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 4/2/2025 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 4/7/2025 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 4/7/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/28/2025 Partial Approval JOSE AVILA
Shower Pan 4/28/2025 Approved JOSE AVILA
Interior/Exterior Lathing 5/7/2025 Approved NICHOLAS TROWBRIDGE
Insulation 5/22/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/28/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 9/29/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 11/20/2025 Approved MATTHEW NELSON
Service/Power Release 12/5/2025 Approved DAVID MATSON
PLUMBING-Final 12/16/2025 Approved MATTHEW NELSON
HVAC-Final 12/30/2025 Approved MATTHEW NELSON