1150 E 49TH ST 90011
Certificate Information: 1150 E 49TH ST 90011
- Application / Permit
- 23010-20000-01236
- Plan Check / Job No.
- B23VN03722
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) **ePlan**
- Permit Issued
- Issued on 9/17/2023
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/24/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/6/2023 | STEVEN KIM |
| Applicant returned to address corrections | 9/6/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/13/2023 | NILOOFAR MEHRAIN |
| Issued | 9/17/2023 | APPLICANT |
| CofO in Progress | 5/6/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/5/2023 | KURT CORRAL |
| Address approval | Cleared | 5/12/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 5/24/2023 | ABEL CASILLAS |
| Low Impact Development (LID) | Cleared | 8/21/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/26/2023 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/15/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/22/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 8/22/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/22/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/26/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 9/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/1/2024 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/1/2024 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 2/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/2/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 5/6/2025 | OK to Issue CofO | NICHOLAS LOPEZ |