415 N CARMELINA AVE 90049
Certificate Information: 415 N CARMELINA AVE 90049
- Application / Permit
- 23010-20000-01225
- Plan Check / Job No.
- B23VN03695
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 41'8" X 60'2" TWO STORY SFD WITH ATTACHED TWO CAR GARAGE AND WITH BASEMENT STORAGE ROOM WITH EXTERIOR ACCESS, NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/3/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | RARES BODEA |
| Corrections Issued | 4/3/2023 | RARES BODEA |
| Quality Review Completed | 4/5/2023 | STEVEN KIM |
| Building Plans Picked Up | 4/5/2023 | APPLICANT |
| Applicant returned to address corrections | 8/4/2023 | RARES BODEA |
| Applicant returned to address corrections | 2/14/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/9/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/15/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/21/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/28/2024 | RARES BODEA |
| Plan Check Approved | 7/2/2024 | RARES BODEA |
| Issued | 7/3/2024 | APPLICANT |
| CofO in Progress | 6/30/2026 | KEVIN SARGSYAN |
| Permit Finaled | 7/1/2026 | JUAN VALENZUELA |
| Permit Finaled | 7/1/2026 | JUAN VALENZUELA |
| CofO Issued | 7/1/2026 | JUAN VALENZUELA |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | JASON NG |
| Permit | Cleared | 4/10/2023 | JASON NG |
| Street Frontage | Cleared | 4/10/2023 | JASON NG |
| ZA Case | Cleared | 4/10/2023 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | JASON NG |
| Distance to fire station | Cleared | 5/26/2023 | LAVEON RIDER |
| Hydrant and Access approval | Cleared | 5/26/2023 | LAVEON RIDER |
| Sewer availability | Cleared | 4/1/2024 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 5/29/2024 | ADALBERTO VERA |
| Low Impact Development | Cleared | 6/26/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 6/28/2024 | BRENDEN HAWK |
| GPI Written Notices | Cleared | 7/2/2024 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 7/2/2024 | RARES BODEA |
Contact Information
| Architect | Ungar,, Kenneth Joel; Lic. No.: C21777 | 1173 WESTBEND ROAD WESTLAKE VILLAGE, CA 91362 |
| Contractor | Tatum Construction Inc; Lic. No.: 733806-B | 1909 CENTINELA AVENUE SANTA MONICA, CA 90404 |
| Engineer | Tuchscher,, James; Lic. No.: C77649 | 5318 E 2ND ST., #539 LONG BEACH, CA 90803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/9/2024 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/27/2024 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 4/4/2025 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/9/2025 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 4/11/2025 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 4/17/2025 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/5/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/14/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/20/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/29/2025 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 5/29/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 7/14/2025 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 7/21/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/11/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 8/15/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 8/15/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/4/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 9/4/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 9/4/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/9/2025 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 9/9/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 9/9/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/9/2025 | Partial Approval | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 9/9/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 9/17/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Insulation | 9/18/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/18/2025 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 9/26/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 10/9/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/23/2025 | Approved | KEVIN SARGSYAN |
| Gas Test | 12/26/2025 | Approved | MICHAEL ALLEN |
| Service/Power Release | 1/8/2026 | Partial Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/9/2026 | Partial Approval | KEVIN SARGSYAN |
| Service/Power Release | 2/25/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 3/18/2026 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/19/2026 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 3/23/2026 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/24/2026 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/23/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 6/26/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 6/26/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 6/26/2026 | Approved | KEVIN SARGSYAN |