415 N CARMELINA AVE 90049

Certificate Information: 415 N CARMELINA AVE 90049

Application / Permit
23010-20000-01225
Plan Check / Job No.
B23VN03695
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 41'8" X 60'2" TWO STORY SFD WITH ATTACHED TWO CAR GARAGE AND WITH BASEMENT STORAGE ROOM WITH EXTERIOR ACCESS, NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/3/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 RARES BODEA
Corrections Issued 4/3/2023 RARES BODEA
Quality Review Completed 4/5/2023 STEVEN KIM
Building Plans Picked Up 4/5/2023 APPLICANT
Applicant returned to address corrections 8/4/2023 RARES BODEA
Applicant returned to address corrections 2/14/2024 RARES BODEA
Applicant returned to address corrections 5/9/2024 RARES BODEA
Applicant returned to address corrections 5/15/2024 RARES BODEA
Applicant returned to address corrections 5/21/2024 RARES BODEA
Applicant returned to address corrections 5/28/2024 RARES BODEA
Plan Check Approved 7/2/2024 RARES BODEA
Issued 7/3/2024 APPLICANT
CofO in Progress 6/30/2026 KEVIN SARGSYAN
Permit Finaled 7/1/2026 JUAN VALENZUELA
Permit Finaled 7/1/2026 JUAN VALENZUELA
CofO Issued 7/1/2026 JUAN VALENZUELA

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
BHO/Hillside ordinance Cleared 4/10/2023 JASON NG
Permit Cleared 4/10/2023 JASON NG
Street Frontage Cleared 4/10/2023 JASON NG
ZA Case Cleared 4/10/2023 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 4/17/2023 JASON NG
Distance to fire station Cleared 5/26/2023 LAVEON RIDER
Hydrant and Access approval Cleared 5/26/2023 LAVEON RIDER
Sewer availability Cleared 4/1/2024 ANTHONY MAINEZ
Trees in Parkway Cleared 5/29/2024 ADALBERTO VERA
Low Impact Development Cleared 6/26/2024 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/28/2024 BRENDEN HAWK
GPI Written Notices Cleared 7/2/2024 RARES BODEA
Grading Pre-Inspection Cleared 7/2/2024 RARES BODEA

Contact Information

Architect Ungar,, Kenneth Joel; Lic. No.: C21777 1173 WESTBEND ROAD      WESTLAKE VILLAGE, CA 91362
Contractor Tatum Construction Inc; Lic. No.: 733806-B 1909 CENTINELA AVENUE      SANTA MONICA, CA 90404
Engineer Tuchscher,, James; Lic. No.: C77649 5318 E 2ND ST., #539      LONG BEACH, CA 90803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2024 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/20/2024 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 12/27/2024 Partial Approval KEVIN SARGSYAN
Sewer 4/4/2025 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 4/9/2025 Partial Approval KEVIN SARGSYAN
Underground Mechanical 4/11/2025 Partial Approval HERBERT GIRON
Underground Mechanical 4/17/2025 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 5/5/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 5/14/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 5/20/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/29/2025 Partial Approval HERBERT GIRON
PLUMBING-Rough 5/29/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Partial Approval STEPHANIE SWANSON
Drywall Nailing 7/14/2025 Partial Approval KEVIN SARGSYAN
Underground Mechanical 7/21/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 8/11/2025 Approved HERBERT GIRON
ELECTRICAL-Rough 8/15/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 8/15/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 9/4/2025 Approved HERBERT GIRON
HVAC-Rough 9/4/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 9/4/2025 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/9/2025 Approved KEVIN SARGSYAN
Green Building Rough 9/9/2025 Approved KEVIN SARGSYAN
HVAC-Rough 9/9/2025 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/9/2025 Partial Approval KEVIN SARGSYAN
Verify Sprinkler Sign Off 9/9/2025 Approved KEVIN SARGSYAN
Insulation 9/17/2025 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 9/18/2025 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/18/2025 Partial Approval KEVIN SARGSYAN
Drywall Nailing 9/26/2025 Approved KEVIN SARGSYAN
Shower Pan 10/9/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/23/2025 Approved KEVIN SARGSYAN
Gas Test 12/26/2025 Approved MICHAEL ALLEN
Service/Power Release 1/8/2026 Partial Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/9/2026 Partial Approval KEVIN SARGSYAN
Service/Power Release 2/25/2026 Approved KEVIN SARGSYAN
PLUMBING-Final 3/18/2026 Approved HERBERT GIRON
ELECTRICAL-Final 3/19/2026 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/23/2026 Approved KEVIN SARGSYAN
ELECTRICAL-Final 3/24/2026 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/23/2026 Not Ready for Inspection KEVIN SARGSYAN
Final 6/26/2026 OK to Issue CofO KEVIN SARGSYAN
Green Building Final 6/26/2026 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/26/2026 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 6/26/2026 Approved KEVIN SARGSYAN