694 N TIGERTAIL ROAD 90049

Certificate Information: 694 N TIGERTAIL ROAD 90049

Application / Permit
23010-20000-01218
Plan Check / Job No.
B23VN03672
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 11' x 21' DETACHED COVERED PATIO WITH ATTACHED DECK
Permit Issued
Issued on 12/22/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 SELLA BENYAMIN
Corrections Issued 4/4/2023 SELLA BENYAMIN
Quality Review Completed 4/6/2023 STEVEN KIM
Building Plans Picked Up 4/7/2023 APPLICANT
Plan Check Approved 7/7/2023 SELLA BENYAMIN
Issued 12/22/2023 APPLICANT
CofO in Progress 4/17/2026 ANDREW NAVE
Permit Finaled 4/21/2026 RICHARD STEINBACH
CofO Issued 4/21/2026 RICHARD STEINBACH
Permit Finaled 4/21/2026 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/11/2023 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 5/17/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 5/17/2023 ANTHONY MAINEZ
Construction near power lines Cleared 6/2/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/28/2023 No Access for Inspection MICHAEL PELHAM
Deputy Reinf. Concrete 1/11/2024 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 1/23/2024 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/23/2024 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/28/2024 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/5/2024 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/6/2024 Conditional Approval CARLOS MATAMOROS
Interior/Exterior Lathing 12/23/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 12/23/2024 Approved CARLOS MATAMOROS
Wood Frame 12/23/2024 Approved CARLOS MATAMOROS
Final 1/12/2026 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 1/12/2026 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/12/2026 SGSOV Not Ready EVAN COOPER
Smoke Detectors 1/12/2026 Approved EVAN COOPER
Final 1/14/2026 No Access for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Not Ready EVAN COOPER
Final 2/3/2026 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Not Ready EVAN COOPER
Final 2/5/2026 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved EVAN COOPER
Final 4/17/2026 OK to Issue CofO ANDREW NAVE