17080-17082 W RAYEN ST 91325
Certificate Information: 17080-17082 W RAYEN ST 91325
- Application / Permit
- 23010-20000-01207
- Plan Check / Job No.
- B23VN03644
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan - (n) single family dwelling per SB9 two unit development per CA govt code 65852.21 at 2nd floor, (n) attached ADU per GCS 65852.2(e)(1)(A) at ground floor R3 occupancy
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | KELVIN CHUONG |
| Corrections Issued | 4/27/2023 | KELVIN CHUONG |
| Quality Review Completed | 5/1/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/16/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 1/30/2024 | KELVIN CHUONG |
| Plan Check Approved | 2/29/2024 | KELVIN CHUONG |
| Issued | 2/29/2024 | APPLICANT |
| CofO in Progress | 3/26/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
| CofO Issued | 4/3/2025 | RUBEN SALAS |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/3/2023 | MEGAN GODINEZ |
| Senate Bill 9 | Cleared | 7/5/2023 | JAZMIN ROQUE |
| Hydrant and Access approval | Cleared | 8/2/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 11/14/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/21/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/2/2024 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 10/2/2024 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/4/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 11/4/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 11/6/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 11/15/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/15/2024 | Approved | MISAEL ESPARZA |
| Sewer | 11/15/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/20/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 11/20/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/20/2024 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 11/20/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 11/20/2024 | Partial Inspection | JAVIER RAMOS JR |
| Special/Order Compliance | 12/4/2024 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 12/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/12/2024 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 12/12/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/19/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/19/2024 | Not Ready for Inspection | MICHAEL CORTEZ |
| ELECTRICAL-Final | 3/17/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 3/17/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 3/17/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/17/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/17/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/17/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 3/26/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 3/26/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 3/26/2025 | Approved | CHRISTOPHER ROJAS |