9232 N NATICK AVE 91343

Certificate Information: 9232 N NATICK AVE 91343

Application / Permit
23010-20000-01201
Plan Check / Job No.
B23VN03627
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY DETACHED ACCESSORY DWELLING UNIT AND OPEN TRELLIS (PER LAMC 12.22 A.33(c) and (d)).
Permit Issued
Issued on 12/7/2023
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 DAWN MC NULTY
Corrections Issued 4/17/2023 DAWN MC NULTY
Quality Review Completed 4/19/2023 STEVEN KIM
Applicant returned to address corrections 8/17/2023 DAWN MC NULTY
Plan Check Approved 11/21/2023 DAWN MC NULTY
Issued 12/7/2023 APPLICANT
CofO in Progress 12/31/2025 MATTHEW NELSON
Permit Finaled 1/2/2026 RUBEN SALAS
CofO Issued 1/2/2026 RUBEN SALAS
Permit Finaled 1/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/10/2023 TAL SHEMEN
Permit Cleared 7/10/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/27/2023 TAL SHEMEN
Sewer availability Cleared 7/27/2023 TAL SHEMEN
Hydrant and Access approval Cleared 8/8/2023 KURT CORRAL
Construction near power lines Cleared 9/23/2023 WALTER RAMIREZ
Construction within easement Cleared 9/23/2023 WALTER RAMIREZ
Low Impact Development (LID) Cleared 11/17/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 11/20/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/17/2024 Partial Approval CHRISTOPHER ROJAS
Pre-Inspection 1/25/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 1/29/2024 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 1/31/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/31/2024 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 2/14/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/22/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Corrections Issued KIRK SANDERS
Verify Sprinkler Sign Off 4/22/2024 Not Ready for Inspection KIRK SANDERS
Wood Frame 4/22/2024 Not Ready for Inspection KIRK SANDERS
Deputy Wood Construction 4/24/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval MATTHEW NELSON
Wood Frame 4/25/2024 Partial Approval MATTHEW NELSON
PLUMBING-Rough 8/5/2024 Approved GREGG CUMMINGS
ELECTRICAL-Rough 9/18/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Approved VINCENT HANLEY
HVAC-Rough 9/18/2024 Corrections Issued VINCENT HANLEY
HVAC-Rough 9/25/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/4/2024 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 10/15/2024 Conditional Approval MATTHEW NELSON
Wood Frame 10/15/2024 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/25/2024 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 10/25/2024 Not Ready for Inspection VINCENT HANLEY
Wood Frame 10/25/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/28/2024 Approved VINCENT HANLEY
Green Building Rough 10/28/2024 Approved VINCENT HANLEY
Green Building Rough 10/29/2024 Approved VINCENT HANLEY
Insulation 11/26/2024 Corrections Issued VINCENT HANLEY
Shower Pan 11/26/2024 Approved VINCENT HANLEY
Drywall Nailing 12/23/2024 Conditional Approval RUBEN SALAS
Interior/Exterior Lathing 1/2/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/14/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 5/15/2025 Corrections Issued VINCENT HANLEY
Drywall Nailing 8/14/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 8/14/2025 Corrections Issued VINCENT HANLEY
Final 8/14/2025 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 8/14/2025 Approved VINCENT HANLEY
HVAC-Final 8/14/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 8/14/2025 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 8/14/2025 Approved VINCENT HANLEY
Final 11/14/2025 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Approved MICHEL ABAJAN
Service/Power Release 11/14/2025 Not Ready for Inspection MICHEL ABAJAN
Final 12/3/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 12/3/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/12/2025 Approved MATTHEW NELSON
Final 12/12/2025 Partial Approval MATTHEW NELSON
PLUMBING-Final 12/12/2025 Approved MATTHEW NELSON
Service/Power Release 12/12/2025 Approved MATTHEW NELSON
Final 12/31/2025 OK to Issue CofO MATTHEW NELSON