226-228 E 82ND ST 90003

Certificate Information: 226-228 E 82ND ST 90003

Application / Permit
23010-20000-01196
Plan Check / Job No.
B23VN03619
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 9/5/2023
Issuing Office
Current Status
CofO Issued on 3/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 CARLOS MONTES
Corrections Issued 4/2/2023 CARLOS MONTES
Quality Review Completed 4/9/2023 PRANITA SHAH
Plan Check Approved 5/26/2023 CARLOS MONTES
Issued 9/5/2023 APPLICANT
CofO in Progress 3/6/2024 MICHAEL LEWIS
CofO Issued 3/12/2024 DEROLD HAUFF
Permit Finaled 3/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/26/2023 MELINEH AGHAKHABIAN
Address approval Cleared 4/29/2023 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 5/5/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 5/5/2023 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 5/13/2023 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 5/15/2023 LAVEON RIDER

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/21/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 9/21/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval MICHAEL LEWIS
Sewer 9/27/2023 Approved MICHAEL LEWIS
Underground Mechanical 9/27/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Partial Approval MICHAEL LEWIS
Insulation 10/2/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Approved MICHAEL LEWIS
Deputy Wood Construction 11/2/2023 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Approved MICHAEL LEWIS
HVAC-Rough 11/21/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 11/21/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/22/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 11/22/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/29/2023 Approved MICHAEL LEWIS
Green Building Rough 11/29/2023 Approved MICHAEL LEWIS
Insulation 11/29/2023 Approved MICHAEL LEWIS
Drywall Nailing 12/12/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/12/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/28/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 1/30/2024 Partial Approval MICHAEL LEWIS
ELECTRICAL-Final 3/4/2024 Approved MICHAEL LEWIS
HVAC-Final 3/4/2024 Approved MICHAEL LEWIS
Service/Power Release 3/4/2024 Approved MICHAEL LEWIS
Final 3/5/2024 OK to Issue CofO MICHAEL LEWIS
Gas Test 3/5/2024 Approved MICHAEL LEWIS
Green Building Final 3/5/2024 Approved MICHAEL LEWIS
PLUMBING-Final 3/5/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 3/5/2024 Approved MICHAEL LEWIS
Smoke Detectors 3/5/2024 Approved MICHAEL LEWIS