15838 W MARLIN PL 91406

Certificate Information: 15838 W MARLIN PL 91406

Application / Permit
23010-20000-01180
Plan Check / Job No.
B23VN03563
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ADU (39'-0"x23'-1"), 1169 SQFT PER LAMC 12.22 A.33(c)(e)
Permit Issued
Issued on 6/22/2023
Issuing Office
Current Status
CofO Issued on 12/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 PETER MOSESIAN
Corrections Issued 3/26/2023 PETER MOSESIAN
Quality Review Completed 3/29/2023 OMID HEDAYAT
Building Plans Picked Up 3/31/2023 APPLICANT
Plan Check Approved 6/2/2023 PETER MOSESIAN
Issued 6/22/2023 APPLICANT
CofO in Progress 12/4/2024 SALVADOR MARTINEZ
Permit Finaled 12/15/2024 RUBEN SALAS
CofO Issued 12/15/2024 RUBEN SALAS
Permit Finaled 12/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/22/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/22/2023 CARLOS AGUILERA
Sewer availability Cleared 4/22/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 5/25/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/26/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/11/2023 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 12/18/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 12/18/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 1/11/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/26/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval RAUL OLAGI
Sewer 4/19/2024 No Access for Inspection RAUL OLAGI
BUILDING-Rough-Frame 5/14/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/14/2024 Corrections Issued RAUL OLAGI
HVAC-Rough 5/14/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/14/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 5/29/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/29/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Approved RAUL OLAGI
HVAC-Rough 5/29/2024 Approved RAUL OLAGI
PLUMBING-Rough 5/29/2024 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 5/29/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/10/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/10/2024 Approved RAUL OLAGI
Green Building Rough 6/10/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 6/10/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 6/18/2024 Approved RAUL OLAGI
Green Building Rough 6/18/2024 Approved RAUL OLAGI
Insulation 6/18/2024 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 6/18/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 6/18/2024 Approved RAUL OLAGI
Insulation 6/21/2024 Approved RAUL OLAGI
Drywall Nailing 7/1/2024 Approved RAUL OLAGI
Shower Pan 7/10/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 7/15/2024 Approved SALVADOR MARTINEZ
Gas Test 7/18/2024 Corrections Issued SALVADOR MARTINEZ
Gas Test 7/25/2024 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 7/31/2024 Partial Approval RAUL OLAGI
Underground Mechanical 8/16/2024 Approved RAUL OLAGI
Final 11/25/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/25/2024 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready SALVADOR MARTINEZ
Service/Power Release 11/25/2024 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 11/25/2024 Approved SALVADOR MARTINEZ
Final 12/3/2024 OK to Issue CofO SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 12/3/2024 Approved SALVADOR MARTINEZ