15838 W MARLIN PL 91406
Certificate Information: 15838 W MARLIN PL 91406
- Application / Permit
- 23010-20000-01180
- Plan Check / Job No.
- B23VN03563
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ADU (39'-0"x23'-1"), 1169 SQFT PER LAMC 12.22 A.33(c)(e)
- Permit Issued
- Issued on 6/22/2023
- Issuing Office
- Current Status
- CofO Issued on 12/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | PETER MOSESIAN |
| Corrections Issued | 3/26/2023 | PETER MOSESIAN |
| Quality Review Completed | 3/29/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 3/31/2023 | APPLICANT |
| Plan Check Approved | 6/2/2023 | PETER MOSESIAN |
| Issued | 6/22/2023 | APPLICANT |
| CofO in Progress | 12/4/2024 | SALVADOR MARTINEZ |
| Permit Finaled | 12/15/2024 | RUBEN SALAS |
| CofO Issued | 12/15/2024 | RUBEN SALAS |
| Permit Finaled | 12/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/22/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 5/25/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/26/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2023 | Approved | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 12/18/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 1/11/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 4/19/2024 | No Access for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/14/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/14/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 5/14/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/14/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/29/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/29/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/29/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/29/2024 | Corrections Issued | RAUL OLAGI |
| Verify Sprinkler Sign Off | 5/29/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/10/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 6/10/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 6/10/2024 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 6/10/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 6/18/2024 | Approved | RAUL OLAGI |
| Insulation | 6/18/2024 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 6/18/2024 | Approved | RAUL OLAGI |
| Insulation | 6/21/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 7/1/2024 | Approved | RAUL OLAGI |
| Shower Pan | 7/10/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 7/15/2024 | Approved | SALVADOR MARTINEZ |
| Gas Test | 7/18/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Gas Test | 7/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 7/31/2024 | Partial Approval | RAUL OLAGI |
| Underground Mechanical | 8/16/2024 | Approved | RAUL OLAGI |
| Final | 11/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 11/25/2024 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Service/Power Release | 11/25/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 11/25/2024 | Approved | SALVADOR MARTINEZ |
| Final | 12/3/2024 | OK to Issue CofO | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 12/3/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 12/3/2024 | Approved | SALVADOR MARTINEZ |