12329 W SATICOY ST 91605

Certificate Information: 12329 W SATICOY ST 91605

Application / Permit
23010-20000-01145
Plan Check / Job No.
B23VN03490
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW DETACHED 12'X33' ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER WFPP. SEE COMMENTS.
Permit Issued
Issued on 8/4/2023
Issuing Office
Current Status
CofO in Progress on 5/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/20/2023 APPLICANT
Assigned to Plan Check Engineer 3/22/2023 HAYATO TSUCHIYA
Corrections Issued 3/22/2023 HAYATO TSUCHIYA
Building Plans Picked Up 3/23/2023 APPLICANT
Applicant returned to address corrections 7/25/2023 GIOVANNY CHAVEZ
Applicant returned to address corrections 7/28/2023 MOHAMMAD ESMAILI
Plan Check Approved 8/2/2023 MOHAMMAD ESMAILI
Issued 8/4/2023 APPLICANT
CofO in Progress 5/29/2026 MATTHEW NELSON

Permit Application Clearance Information

Address approval Cleared 4/12/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 6/12/2023 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 6/20/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 7/21/2023 ROMAN GUTIERREZ
Sewer availability Cleared 7/25/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/16/2023 Partial Inspection WILLIAM WREN
Sewer 10/24/2023 Partial Inspection KEVIN BERBERYAN
Underground Mechanical 10/24/2023 Partial Inspection KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 11/6/2023 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/6/2023 Not Ready for Inspection CHRISTOPHER ROJAS
METHANE-Barrier 11/6/2023 Approved CHRISTOPHER ROJAS
METHANE-Subgrade 11/6/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/9/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 11/9/2023 Not Ready for Inspection CHRISTOPHER ROJAS
METHANE-Rough 11/9/2023 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 11/9/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/29/2023 Partial Approval MATTHEW NELSON
Insulation 11/29/2023 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 12/1/2023 Approved MATTHEW NELSON
HVAC-Rough 12/1/2023 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 12/1/2023 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 12/15/2023 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 1/18/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 1/18/2024 Approved MATTHEW NELSON
HVAC-Rough 1/18/2024 Not Ready for Inspection MATTHEW NELSON
Insulation 1/18/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 1/18/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/24/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 1/24/2024 Approved MATTHEW NELSON
HVAC-Rough 1/24/2024 Approved MATTHEW NELSON
Insulation 1/24/2024 Approved MATTHEW NELSON
Drywall Nailing 2/6/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/6/2024 Approved MATTHEW NELSON
Final 3/7/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 3/7/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 3/7/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 3/7/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 3/21/2024 Corrections Issued MATTHEW NELSON
Green Building Final 3/21/2024 Approved MATTHEW NELSON
Service/Power Release 3/21/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 3/21/2024 Approved MATTHEW NELSON
Final 1/28/2026 No Access for Inspection MATTHEW NELSON
Service/Power Release 1/28/2026 No Access for Inspection MATTHEW NELSON
Final 2/2/2026 No Access for Inspection MATTHEW NELSON
Service/Power Release 2/2/2026 No Access for Inspection MATTHEW NELSON
Final 2/4/2026 Corrections Issued MATTHEW NELSON
Service/Power Release 2/4/2026 Not Ready for Inspection MATTHEW NELSON
Final 2/9/2026 Corrections Issued MATTHEW NELSON
Service/Power Release 2/9/2026 Corrections Issued MATTHEW NELSON
Final 2/11/2026 Corrections Issued MATTHEW NELSON
Service/Power Release 2/11/2026 Not Ready for Inspection MATTHEW NELSON
Final 5/28/2026 OK to Issue CofO MATTHEW NELSON
Service/Power Release 5/28/2026 Approved MATTHEW NELSON